Scheldt Tunnel partly submerged on the Left Bank

Work on the new Scheldt Tunnel is progressing rapidly. At the construction site on the Left Bank, the first section* of the tunnel is currently being submerged. The next step will be breaching the old Scheldt dike.
With the new Scheldt Tunnel, we are not only building a much-needed connection between the Left and Right Banks. We are also using the works to better protect inland areas against flooding. We are doing this by giving the Scheldt more space, creating a natural floodplain. Further inland, we are building a new, higher Scheldt dike.
The construction of the Scheldt Tunnel will create 24 hectares of high-quality natural habitat close to the city, equivalent to no fewer than 34 football pitches: 18 hectares of tidal mudflats and marshes, and 6 hectares of floodplain woodland close to the river.
We are currently making good progress on the entrances and exits to the new Scheldt Tunnel on both the Left and Right Banks. On the Scheldt side of the Left Bank, work on the first tunnel section has been completed, and we are now flooding this part of the construction site. “We are pumping no fewer than 150,000 m³ of water from the river into the site. This is an important milestone for the site: the tunnel and the Scheldt are meeting for the first time,” explains Maarten Pombreu, project manager at Lantis.
New Scheldt dike protects inland areas against flooding
We have built a new Scheldt dike around 300 metres inland. It is 2.5 metres higher and forms part of the Sigma Plan to better protect Flanders against flooding. Flooding the construction site is the next step towards breaching the old dike next year.
Elke Rombaut, Earthworks and Dredging Project Manager at TM COTU: “We cannot simply breach the old dike because of the strong current in the Scheldt. Doing so could damage the tunnel. That is why we are flooding the tunnel first, before excavating the old dike. We will breach the old dike in early 2025, making the expansion of the Scheldt a reality.”
In summer 2025, the tunnel sections will travel one by one from Zeebrugge to Antwerp. We will then connect the first tunnel element to the Left Bank. The connection will be ready for cyclists in 2028. Two years later, in 2030, the tunnel will open to motorised traffic.

*The other eight sections of the Scheldt Tunnel were built in a construction dock in Zeebrugge. The tunnel sections are currently being prepared for their journey from the coast to Antwerp, via the North Sea and the Scheldt.
Question about this story? Ask your question
Who worked on Scheldetunnel
- contractorTM COTUMentioned in Transporting the Scheldt Tunnel’s giant elements: preparations in full swing
- bouwkuipstempelingAlmex MetaalMentioned in Transporting the Scheldt Tunnel’s giant elements: preparations in full swing
- clientLantisMentioned in Transporting the Scheldt Tunnel’s giant elements: preparations in full swing
Keep following this
Get an email when a new story is published. No account needed.
- ProjectScheldetunnel
- ThemeExtending the life of bridges and tunnels
- SubjectBridges & tunnels