A crucial link in the electricity grid of the future
Text Joris Hendrickx Beeld Deschacht

The energy transition calls for stronger, future-proof infrastructure. A prime example is the major Elia project between Zottegem and Aalst, where a new underground high-voltage connection is being built. To carry out the horizontal drilling, contractor BESIX UNITEC is drawing on Deschacht’s expertise to supply no fewer than 22 kilometres of cable protection ducts.
The project is part of the renewal and reinforcement of the electricity grid between the Zottegem and Aalst high-voltage substations. The existing overhead high-voltage line is being replaced with a new underground connection designed to meet the region’s future energy needs.

Impressive scale
With a total of 22 kilometres of cable protection ducts, this project ranks among the larger HDD (Horizontal Directional Drilling) applications in Flanders. The drilling is being carried out by BESIX UNITEC, under the direction of project manager Edis Karadan.
Horizontal directional drilling makes it possible to complete long routes with minimal impact on the surrounding area, infrastructure and traffic. This technique offers an efficient solution for installing utility pipelines in locations where traditional open trenches are less suitable.
Edis Karadan: “This project perfectly demonstrates where directional drilling makes a difference today. Over a route spanning tens of kilometres, we can install a new high-voltage connection with minimal impact on the surrounding area.”

Quality as the starting point
For this project, BESIX UNITEC deliberately chose PE100 Virgin pipes. These pipes are manufactured without recycled material, ensuring consistent, high quality. Their properties are comparable to those of a BENOR-certified pipe, providing an important guarantee for a project with such a long service life and strategic importance.
Deschacht was responsible not only for supplying the pipes, but also for organising the logistics and unloading them on site. Ensuring the materials were readily available was essential to support the tight drilling schedule.

Trust as the basis for collaboration
In addition to the technical specifications, the long-standing collaboration between Deschacht and BESIX UNITEC also played an important part in securing this contract. The strong relationship between Deschacht account manager Jeroen Walgraeve and the BESIX UNITEC team helped lay the foundations for a successful partnership. A competitive price, combined with technical support, reliable deliveries and mutual trust, was decisive in choosing Deschacht as a partner for this prestigious infrastructure project.
“Strong collaboration with our suppliers is crucial to the successful delivery of a project on this scale. Deschacht stands out for its flexibility, prompt follow-up and ability to work with us to find the best possible solution,” says project manager Edis Karadan.

Building the energy grid of tomorrow
By supplying 22 kilometres of cable protection ducts, Deschacht is making a direct contribution to a project that will increase the reliability and capacity of the Belgian electricity grid. In time, the new underground connection will be able to transmit more electricity than the existing overhead line, making it an important investment in the energy supply of the future.
This project once again shows how quality products, technical expertise and strong partnerships make a difference on complex infrastructure projects.

Een zakelijke vraag aan Deschacht? Get in touch
Who worked on it
Elia-project
- kabelbeschermbuizen
Deschacht - contractorBESIX UNITEC
Keep following this
Get an email when a new story is published. No account needed.
- ProjectElia-project
- ThemeUsing and protecting the subsurface
- SubjectSewerage & underground infrastructure
- CompanyDeschacht
- CompanyBESIX UNITEC