Bridges & tunnels

Integral bridge replaces ageing Bailey bridge in Mendonk

Text Joris Hendrickx Beeld Herbosch-Kiere

De nieuwe Spanjeveerbrug opent naar verwachting eind 2026.
De nieuwe Spanjeveerbrug opent naar verwachting eind 2026.

The old Spanjeveerbrug over the Moervaart in Mendonk is making way for a replacement designed to meet future needs. The new bridge addresses the limitations of the old structure and provides a smoother, safer connection. Site manager Peter-Paul de Beukelaar (Herbosch-Kiere) gives an insight into the approach and the challenges on site.

The end of a ‘temporary’ solution

The existing bridge dated from the 1970s and was never intended as a permanent solution. “It was a Bailey bridge with a 2.5-tonne weight limit,” says De Beukelaar. “It was narrow and low, and only allowed traffic to pass in alternating directions. But above all, the bridge had simply reached the end of its life.”

Despite this, it continued to carry heavy traffic. De Beukelaar says urgent action was therefore needed: “Employees of nearby businesses in particular use this route as a shortcut. That placed an additional burden on a structure that was not designed for it. De Vlaamse Waterweg therefore decided to replace the bridge entirely.”

The bridge will be slightly wider, but will still have just one lane.

A new bridge without restrictions

The new bridge is being built in the same location, with a similar span. However, it brings clear improvements. “The bridge itself will be slightly wider, but will still have just one lane. The approach ramps, on the other hand, have been widened sufficiently to allow vehicles to pass each other smoothly,” explains De Beukelaar.

The design differs considerably from the old structure in technical terms. “It is an integral bridge design with no bearings. We accommodate movement through the foundation piles. This makes the bridge simpler and easier to maintain.” De Vlaamse Waterweg provided the outline design. Herbosch-Kiere then developed it further. “Together with an engineering consultancy, we carried out all the calculations and sizing down to the smallest detail.”

The new bridge is being built in the same location, with a similar span.

A solid new foundation

Work began in August 2025 with the demolition of the old bridge. It was completely removed and taken away for scrap. Construction of the new structure then began. De Beukelaar: “First came the sheet piles and cofferdams. Our team then installed tubular piles for the foundations. We built the abutments on these, followed by the girders.”

A temporary footbridge alongside the site ensures access for vulnerable road users.

Heavy lifting as a key milestone

Installing the steel girders was a crucial stage. “The bridge consists of two large girders, each made up of two sections welded together at our yard in Kallo. They were then brought to the site by pontoon,” says De Beukelaar. The heavy lifting followed on site. “We used two cranes: one with a capacity of 700 tonnes and one of 500 tonnes. These are not everyday machines. The girders had to be positioned correctly in a single lift.” De Beukelaar says this was a decisive moment. “It is a key milestone. Everything has to be right: timing, stability and communication.”

The formwork is suspended from the structure itself, with HEA sections spanning the girders.

On track to open in late 2026

The bridge deck was installed after the girders were in place. The formwork is suspended from the structure itself, with HEA sections spanning the girders. “This approach required additional effort. Each formwork panel had to be cast and aligned separately using the traditional method. There was also limited working height beneath the bridge,” says De Beukelaar. The bridge deck was poured at the end of March 2026. “Despite the labour-intensive and complex working method, we are keeping to schedule. We are now continuing with the finishing work on the bridge and its surroundings. The new Spanjeveerbrug is expected to open in late 2026.”

It is an integral bridge design with no bearings.

Een zakelijke vraag aan Herbosch-Kiere? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectSpanjeveerbrug
  • ThemeExtending the life of bridges and tunnels
  • SubjectBridges & tunnels
  • CompanyHerbosch-Kiere
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.