Wijnegem cycle bridge completes major Albert Canal bridge programme
Text Joris Hendrickx Beeld De Vlaamse Waterweg nv

More room for inland shipping, better cycling links and bridges fit for the future. Raising the bridges over the Albert Canal grew into one of Flanders’ largest infrastructure programmes. Sweco, together with Arcadis, supported De Vlaamse Waterweg nv in upgrading 31 bridges. The recent opening of the new cycle and pedestrian bridge in Wijnegem marked the final piece of the programme. Inge Vervaet of Sweco and Stefan Sablon of De Vlaamse Waterweg nv look back on a programme that continually combined considered standardisation with bespoke solutions.

Four container layers as the starting point
The Albert Canal is a vital link between the Port of Antwerp and the industrial area around Liège. Back in the 1990s, De Vlaamse Waterweg nv identified the potential to carry more containers by inland waterway. New bridges were therefore designed with sufficient headroom for four layers of containers.
This approach gathered pace from 2009. Bridges were no longer replaced only when they had reached the end of their service life. The Flemish Government opted to systematically raise and widen every bridge over the canal. “A minimum clearance of 9.10 metres allows four layers of containers,” says Stefan Sablon. “At the same time, we wanted to remove the historic bottlenecks at the bridges, so push-tow convoys could pass each other there safely and comfortably.”
In 2014, De Vlaamse Waterweg nv brought in Sweco, in a temporary joint venture with Arcadis. “There were still 31 bridges to tackle,” says Inge Vervaet. “The brief was clear: we had to turn that ambition into concrete projects as quickly as possible. The bridges had to be designed, permitted, tendered and built. The programme was largely delivered in just 10 years. Wijnegem now marks its final piece.”

One bridge design, a different setting every time
For many locations, De Vlaamse Waterweg nv chose a generic bridge design, developed in collaboration with the Flemish Government Architect. Its distinctive form was intended to create a recognisable signature along the Albert Canal. Standardisation also brought technical advantages. Sablon says: “We could replicate the design, reducing the risk of errors and cutting design and construction costs. It also has advantages for maintenance. The same principles are used each time.” At the same time, the bridge had to be understated enough to suit a range of settings.
A standard bridge did not mean a standard approach, however. “Every location started with the same objectives, but then we looked at its context,” says Vervaet. “Is the bridge in an urban, rural or industrial area? What are the traffic flows? What do local authorities and residents need? A bridge may be there for a hundred years, so you have to look beyond today’s situation.”
Experience from each project also fed into the next bridges. “That learning process was very important,” Vervaet adds. “We carried forward anything that could have been done better on the previous bridge. That improved not only the bridges, but also how we integrated and built them.”
Minimising disruption starts before the design
Inland shipping had to keep operating as far as possible during the works. After all, the Albert Canal is a key economic transport route. “We first agreed with the operations team on what level of disruption was acceptable. Then we looked at how to build within those limits. Initially, closures were limited to 24 hours, often on Sundays or public holidays. Later, the canal moved to 24/7 operations,” says Sablon.
“That made every interruption more critical. So we grouped work at different bridges together as much as possible. For example, assembling a bridge at one location, demolishing one elsewhere and removing formwork at a third location could all be done on the same day.”
Construction methods also evolved. “Some of the first bridges were demolished by deliberately dropping them into the canal,” says Vervaet. “We then had to dredge everything back out. On later bridges, we made much greater use of controlled demolition methods. Those techniques are now being used in other projects too.”
The same attention was paid to road traffic. Disruption plans brought together requirements from municipalities, De Lijn, AWV and other stakeholders in advance. “Clarity builds support,” stresses Sablon. “If we said a road would be closed for four weeks, it was closed for four weeks. Not six. Say what you’ll do and do what you say: it works.”

Sustainability also means cycling infrastructure, maintenance and soil management
Moving more goods by inland waterway was itself a sustainability goal. But the programme took a broader view. “Whenever we upgraded infrastructure, we used compliant cycling infrastructure as our starting point,” says Sablon. “Separate cycle paths, good widths and gradients, and better connections to the towpaths.”
Service life and maintenance were also given close attention. “The generic bridge concept allows for future modifications,” says Vervaet. “The bridge deck remains relatively flexible in its layout. We also focused closely on maintainability. For example, the maintenance gantries can be used on several bridges. Abutments and bearings are also more accessible. People need to be able to work there safely and ergonomically.”
Soil movements were even considered at programme level. Soil from one project could be used for raising ground levels elsewhere. “You get that benefit when you consider several projects as a whole,” says Sablon. “That helped us minimise transport, CO2 emissions, traffic disruption and costs.”
Wijnegem called for a completely different solution
The programme’s final piece, the cycle and pedestrian bridge in Wijnegem, was one of its most complex locations. The Albert Canal and the busy lock complex literally divide the village in two. The existing ‘Bananenbrug’ offered little comfort for cyclists. “That bridge was very steep,” says Sablon. “There was also an alternative route over the lock complex, but it had stairs, steep gradients and tight bends.”
A mobility study showed that the main cycling flow was at the lock. One new bridge for all traffic was therefore not the best solution. “We split the project,” says Sablon. “Motor traffic was moved around 250 metres downstream. The cycle and pedestrian bridge stayed where the main cycling connection belongs: at the lock.” He says the municipality of Wijnegem also played an important role. “They really engaged as a partner. That strengthened the result.”

A slender design above a busy lock complex
For Sweco, the cycle and pedestrian bridge was a distinctive technical challenge. “It’s a long, slender bridge,” says Vervaet. “The cycle path is six metres wide and fully compliant with the Fietsvademecum. Alongside it is a fully fledged pedestrian zone.” The design has a single pylon between the two locks, with stay cables supporting the deck. The structure had to look slender while remaining technically stable. “You have to account for torsion, wind loading and possible vibrations, among other things,” Vervaet explains. “For some of the challenges, we also sought to work with universities.”
On top of that, disruption to the push-tow lock had to be kept to a minimum. Inspection and maintenance were also considered from the design stage. “The stay cables are anchored at the top of the pylon,” says Vervaet. “They will need to be inspected in the future, so someone has to be able to access the pylon safely. Structural solutions must not block that access.”
3D brings complex decisions into view
Wijnegem also provided lessons for future projects. The design was developed entirely in 3D. “In a setting this complex, it gives you much more insight,” says Sablon. “Not just as a designer, but also for the operations team and local residents.” The 3D images helped answer questions about overlooking and light nuisance from traffic, for example. Virtual viewpoints inside homes showed what residents would see after the works. “That removes a lot of uncertainty,” says Sablon. “You can’t take every concern into account, but you can listen, investigate and explain why something is or isn’t possible.”
For Vervaet, this open-minded approach sums up an important lesson from the programme as a whole. “You shouldn’t automatically keep doing things the way you’ve always done them. Sometimes a different technique turns out to be much more suitable. Keep an open mind and keep looking for ways to improve.” Sablon agrees: “Government, designers, contractors and local authorities each have their own room to manoeuvre. But there’s often scope within those limits. If you listen to one another and look for solutions together, you can achieve more. And it doesn’t even have to cost more.”

Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeExtending the life of bridges and tunnels
- SubjectBridges & tunnels