Striking bridge in Zulte calls for advanced concrete expertise
Text Joris Hendrickx Beeld Herbosch-Kiere

In Zulte, Herbosch-Kiere is building a new bridge for cyclists and pedestrians over the Leie, alongside the creation of 1.6 kilometres of nature-friendly banks. Behind the elegant design lies a technically challenging concrete project. The sloping piers, complex formwork and strict tolerances call for particular expertise. Project manager Stef Buyck explains how Herbosch-Kiere is tackling these challenges.
Commissioned by De Vlaamse Waterweg, Herbosch-Kiere is building a new walking and cycling link near the castle of Zulte and Limnanderdreef. The bridge restores a historic link between the two banks that disappeared when the Leie was canalised. Around 1,600 metres of banks are also being redeveloped as a nature-friendly zone. The project is one of the steps in upgrading the Leie for shipping as part of the Seine Schelde network.

No standard bridge
The bridge consists of a steel central section of around 100 metres, supported by concrete abutments, approach ramps and piers. In architectural terms, the structure echoes the nearby Vlasbrug, also designed by engineering consultancy SBE, combining refined design with demanding structural requirements. Although the brown-red steel structure with its finely meshed balustrade is the most eye-catching feature, Stef Buyck says the biggest technical challenge lies in the concrete works. “The slender-looking steel structure rests on a complex concrete substructure. That makes this project particularly interesting. Almost none of the concrete elements are built to a standard design.”
“On the right bank, in line with the bridge and the avenue, we are building a long approach ramp supported by concrete columns. On the left bank, the bridge ends at a large concrete viewing platform with benches and bicycle racks. On the platform, the cycle path makes a 90-degree turn before descending along the bank, parallel to the Leie, towards the towpath. The bridge connects to the existing cycle network on both sides,” says Buyck.

Sloping piers raise the level of difficulty
The biggest challenge lies in the sloping concrete piers. They are fully formworked, reinforced and cast in situ. Their angled shape means conventional construction methods are not sufficient. “With a vertical pier, gravity works in your favour,” says Buyck. “Here, the entire casting and compaction method has to change. The formwork also requires much more preparation. Everything has to be perfectly aligned.”
On the left bank, the triangular viewing platform is supported by several concrete piers cast in situ. Herbosch-Kiere also developed fully bespoke formwork for these. “The platform has to meet the steel bridge seamlessly. That is why we are working to very tight tolerances. We carefully check every measurement and every casting stage.”

Installation calls for perfect coordination
The concrete works will be followed by installation of the four steel bridge sections, manufactured by CSM in Hamont-Achel. Two sections, each weighing around 50 tonnes, will be installed from the bank using a telescopic crane. The span over the water, comprising sections 3 and 4 with a combined weight of around 100 tonnes, will be installed from the water on 26 September 2026 using Herbosch-Kiere’s sheerleg crane Antigoon.
“An operation like this starts months in advance,” Buyck explains. “The schedule for the concrete works, transport, crane positioning and installation has to be perfectly coordinated. Installation only goes smoothly if all the preparatory work has been completed precisely within the specified tolerances.”

Aesthetics and functionality go hand in hand
The concrete works on the left bank are at an advanced stage. Work on the approach ramps on the right bank will soon be completed. The entire bridge and surrounding works are due for completion in early 2027. “This project clearly shows that water engineering today goes far beyond purely functional infrastructure,” Buyck concludes. “The structure has to be technically perfect while also making a strong architectural statement. It is that combination that makes this project so interesting.”

Een zakelijke vraag aan Herbosch-Kiere? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeExtending the life of bridges and tunnels
- SubjectBridges & tunnels
- CompanyHerbosch-Kiere