Paving the way for the new hospital tower
Text Philippe Selke Beeld Franki Foundations

Before the future hospital tower at Saint-Luc University Hospital can rise from the ground, important work must first be carried out… below ground. As part of the redevelopment of the site, Franki Foundations is working at several locations using a range of ground stabilisation and specialist foundation techniques. What makes this site particularly notable is that the work is being carried out in the middle of a fully operational hospital.
A series of foundation works
The HospitaCité project includes the construction of a new hospital tower and the renovation of the existing medical and technical podium. As part of the works entrusted to Jacques Delens, Franki Foundations is carrying out a series of foundation works in preparation for the future excavation. “The aim is to prepare the excavation pit for the major construction project that follows, namely the construction of the new hospital,” explains Etienne Delheusy, project manager at Franki Foundations.
Work began in November 2025. A new entrance to the existing car park was created using a secant pile wall. The old entrance was within the construction site for the future works. A soil-nailed wall was then built to replace a precast L-shaped retaining wall. This alternative limited the need for terracing with slopes and allowed several trees to be preserved.

Working in an operational hospital
Further work followed: two shored trenches six to seven metres deep in an existing basement, a soil-nailed wall along Hippokrateslaan, and the underpinning of existing buildings and structures.
The challenge is not purely technical. Much of the hospital remains operational close to the site, and this directly affects the construction methods used. “Where we might otherwise have installed a Berlin-type retaining wall, that is not possible here because the operating theatres are highly sensitive to vibration,” explains Etienne Delheusy.
The work in the basement required further precautions. The work areas are close to loading bays used to supply the hospital. Excavation was therefore carried out under negative pressure to prevent dust from spreading. Some concrete work also had to be done outside working hours, with strict monitoring of carbon monoxide levels.

Diaphragm walls down to the clay layer
The main phase covers an area of around 50 by 170 metres. Diaphragm walls must be installed there to allow excavation for the future basements. The walls will extend down to the clay layer, making it possible to lower the groundwater level during excavation.
The operation also presents a logistical challenge. “It is not easy to get 7,000 to 8,000 m³ of concrete and 20-metre-long reinforcement cages to this site,” emphasises the project manager. The difference in elevation of around ten metres between Hippokrateslaan and E. Mounierlaan makes planning even more complex. The platforms must be wide and stable enough to accommodate the machinery, and must be prepared in sequence to ensure the work can continue uninterrupted.

More stringent design requirements
In addition to these constraints, the future hospital building is subject to specific structural requirements. While many structures are generally assigned to consequence class CC2, these structures are designed to CC3. Additional safety factors must therefore be applied to the secant piles and diaphragm walls, in accordance with the specification and the requirements of engineering consultancy Sweco and technical inspection body SECO.
Some underpinning work also extends to a depth of 15 metres. It must extend the foundations of the existing buildings to the level required for the future excavation. “That means we have to excavate by hand to a depth of 15 metres,” explains Etienne Delheusy.
Franki Foundations’ work is expected to continue until after the summer of 2027. This underground phase will largely be out of sight in the long term, but is essential before the new hospital tower can take shape.
Question about this story? Ask your question
Who worked on it
HospitaCité
- foundation worksFranki Foundations
- engineering consultancySweco
- technisch controlebureauSECO
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHospitaCité
- ThemeUsing and protecting the subsurface
- SubjectFoundation engineering
- CompanyFranki Foundations
- CompanySweco
- CompanySECO