Giants on the way: Scheldt Tunnel entrance on the Left Bank ready to receive eight tunnel sections

First-ever visit to the mouth of the Scheldt Tunnel on the Left Bank
Lantis and contractor TM COTU* have taken another step forward in building the Scheldt Tunnel: the structural works on the tunnel entrance on the Left Bank are complete. This means that, together with the eight gigantic concrete tunnel sections in Zeebrugge and the base of the tunnel approach on the Right Bank, the essential components of the Scheldt Tunnel are now ready. Minister Annick De Ridder walked through the entrance to the Scheldt Tunnel for the first time today.

Scheldt Tunnel entrance on the Left Bank ready
After more than three years of preparation and intensive construction work, the essential components of the Scheldt Tunnel are ready. The structural works on the tunnel entrance on the Left Bank have just been completed. “A total of 85,000 m³ of concrete and 19,000 tonnes of steel were needed to build this 486-metre-long section of tunnel,” says Maarten Pombreu, project manager at Lantis. “We are now continuing work here on the connection to the Sint-Anna interchange on the Left Bank.” Concrete works on the Right Bank are also progressing well. The final tunnel section will connect to it at the end of 2025.

Giants on the way
Together with the eight concrete tunnel sections waiting in Zeebrugge, all the pieces of the puzzle for the Scheldt Tunnel are now ready. Each tunnel section is bigger than a football pitch, longer than the tallest cathedral, a true giant. They weigh an average of 60,000 tonnes and measure 160 metres long, 42 metres wide and 10 metres high. These are real giants, and this year they will make their way to Antwerp one by one. They will make a spectacular journey of more than 100 kilometres across the North Sea and along the Scheldt.
The large-scale logistical operation required involves numerous technical challenges. From controlled transport across the North Sea and along the Scheldt to the complex underwater installation, every step calls for meticulous preparation and collaboration between various parties.
Raymond de Kroon, Project Director for Execution at TM COTU: “According to the current schedule, we will flood the construction dock in Zeebrugge on 11 April. At that point, the ballast tanks in the eight tunnel sections will also contain water. This will keep them on the bottom,” says Raymond. “On 19 May, it will be time for the first tunnel section to depart. We will then pump the water out of the ballast tanks so that the section rises to the surface. In short, that is Archimedes’ principle in a nutshell.”
“The schedule depends on a whole range of conditions, such as the weather, wind strength, wave action and tides,” Raymond continues. “We continuously assess the forecasts and compare them with the actual conditions at the time of execution. To prepare for these conditions, we use advanced simulations that map out the entire journey in detail. In these simulations, skippers train not only in manoeuvring and navigating in response to these factors, but also in crisis management, communication and collaboration.”

30 hours on the move
The journey from Zeebrugge to the Doeldok in Antwerp takes around 30 hours for each tunnel section. Along the way, each section stops twice, once in the outer harbour of Zeebrugge and once in Terneuzen. They do this to wait for the incoming tide, so they can travel with the current.
The tunnel sections are also held in the Doeldok because of the tides. They can only be lowered into place around neap tide, when the difference between high and low water is at its smallest. This occurs only twice a month, around the first and last quarter of the moon. Lantis and TM COTU are aiming for early July for the first lowering operation. By the end of the year, all eight tunnel sections will be in place and finishing work on the tunnel can begin.

Only possible through collaboration
An impressive journey for these concrete giants, but at least equally impressive are the people of flesh and blood working on the project. “A project on this scale can only be delivered through close collaboration between many parties,” says Jonas Rabaey, environment manager at Lantis. “From engineers and construction workers to tugboat captains and safety coordinators, everyone plays a crucial role. We also need to coordinate, plan and work together continuously with stakeholders and external parties.”

A unique operation for all of Flanders
Annick De Ridder, Minister for Mobility and Public Works: “All the pieces of the puzzle are ready, and we can now start putting them together so that the tunnel can open fully in 2030. In doing so, we are not only creating a literal connection between the Left Bank and the Right Bank, but also bringing together the expertise and knowledge that have made this technical feat possible. I always say, without hesitation, that we are building the construction site of the century here. Because people in Flanders can sometimes be a little hesitant to say so. They shouldn’t be. We should be proud that here in our small Flanders we can deliver such a major project.”
With this project, Lantis also wants to get people in Flanders excited about the enormous expertise and knowledge involved in building the Scheldt Tunnel. That is why the “Giants on the Way” campaign starts today, featuring striking images that convey the scale of the operation. You can follow all the latest updates on the project at www.kanjersopkomst.be.

New Scheldt Tunnel helps complete the Ring
The Scheldt Tunnel is a vital link in the Oosterweel Link. The new tunnel connects both banks of the Scheldt, helping to complete the Antwerp Ring to the north of the city, together with the Oosterweel interchange and the Canal Tunnels. The result: smoother, safer traffic to and around Antwerp. The Scheldt Tunnel will open to cyclists in 2028. From 2030, it will also connect the motorways on the Left Bank with the port and the north of the city for cars and lorries.
*TM COTU stands for Tijdelijke Maatschap Combinatie Oosterweeltunnel. The group consists of Belgian construction companies BESIX, Stadsbader Contractors, DEME and Jan De Nul.

Question about this story? Ask your question
Who worked on Scheldetunnel
- contractorTM COTUMentioned in Transporting the Scheldt Tunnel’s giant elements: preparations in full swing
- bouwkuipstempelingAlmex MetaalMentioned in Transporting the Scheldt Tunnel’s giant elements: preparations in full swing
- clientLantisMentioned in Transporting the Scheldt Tunnel’s giant elements: preparations in full swing