Storm surge barrier in Nieuwpoort will be a first for Belgium
Text Joris Hendrickx Beeld Herbosch-Kiere

With the storm surge barrier in Nieuwpoort, a crucial link in coastal protection, Flanders is setting a new standard in climate-resilient infrastructure. Frederik Bourgois, project manager at Herbosch-Kiere, talks about the challenges and innovative solutions involved in this complex project.
With the storm surge barrier in Nieuwpoort, a crucial link in coastal protection, Flanders is setting a new standard in climate-resilient infrastructure. Frederik Bourgois, project manager at Herbosch-Kiere, talks about the challenges and innovative solutions involved in this complex project.
The storm surge barrier is an integral part of the Masterplan Kustveiligheid. Located in the port channel at Nieuwpoort, where the River IJzer meets the sea, the tilting barrier forms an important line of defence against severe storm surges. It has been designed with the long term in mind. Bourgois says: “We are building a structure that can not only meet today’s challenges, but also withstand the future impacts of climate change. It is a first for our country.”
Rising sea levels and an increasing number of storms caused by climate change mean that robust coastal protection is more important than ever. “The storm surge barrier in Nieuwpoort is a response to these challenges,” explains Frederik Bourgois. “It is designed to withstand storms that occur once every thousand years and to protect against an expected sea-level rise of 80 centimetres by 2100. The project will therefore safeguard the hinterland, more than 85% of which lies below +6 metres TAW.”

A considered, flexible design
“The barrier’s unique design allows it to respond flexibly to changing conditions,” says Bourgois. It consists of a movable steel barrier that pivots between two cast-steel shafts. “In normal conditions, the barrier is concealed in a concrete sill on the bed. In the event of a storm surge, it is smoothly raised into position. The operating mechanism, installed on both sides of the barrier, means it remains operational even if only one system is working.”
Bypass culverts have also been added to minimise the impact on currents in the navigation channel, an important consideration given the nearby marinas. “The tunnel structures, measuring 6.80 by 6.05 metres and 40 metres long, keep the current under control.” Work on the bypass culverts on the right bank is almost complete. Work on the left bank is, as planned, around six weeks behind. “By carrying out the work in phases, we can deploy staff and equipment efficiently and minimise disruption to shipping,” Bourgois explains.

Integrated collaboration
The project is being delivered by a temporary integrated contractor consortium formed by Herbosch-Kiere and Jan De Nul, with costs, resources and expertise shared between them. “This collaboration ensures efficient delivery,” says Bourgois. “We are also working closely with the Agentschap Maritieme Dienstverlening en Kust to ensure that the project is environmentally responsible as well as technically sound.”

Herbosch-Kiere’s distinctive contribution
Together with its partner Jan De Nul, Herbosch-Kiere is the lead contractor in the integrated contractor consortium and is responsible for coordinating the various activities. “Our experience in water engineering is a major asset,” says Bourgois. “From building infrastructure in, over and close to water, maintaining waterways and delivering offshore energy projects to ship salvage, foundation construction and soil remediation, Herbosch-Kiere’s extensive and in-depth expertise is essential for projects of this complexity.”
The concrete sill in which the barrier sits was built on a semi-submersible vessel in Herbosch-Kiere’s docks and transported to the site on a specially designed crane vessel with a capacity of 1,800 tonnes. “It took incredible precision to position it exactly between the two abutments. The sill even contains tunnels that allow equipment and technicians to pass safely underwater from the left bank to the right.”

Een zakelijke vraag aan Herbosch-Kiere? Get in touch
Wie aan Stormvloedkering Nieuwpoort werkte
- temporary partnership
Herbosch-KiereMentioned in Construction of second cofferdam for Nieuwpoort storm surge barrier enters final phase - temporary partnershipJan De Nul GroupMentioned in Construction of second cofferdam for Nieuwpoort storm surge barrier enters final phase
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNieuwpoort storm surge barrier
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering
- CompanyHerbosch-Kiere