Preparing for the future with a new quay at Kanaaldok B2
Text Joris Hendrickx Beeld Herbosch-Kiere

The Antwerp port waterfront is constantly changing. Quay walls are being built or thoroughly refurbished. Herbosch-Kiere plays a prominent role in this process. Based at its strategic hub in Kallo, an experienced team is ready to draw on its many references in quay wall construction and complex port projects. By combining its technical expertise with flexibility, Herbosch-Kiere delivers a tailored solution for every situation. In this way, the company grows alongside a port that never stands still.
Herbosch-Kiere is currently building a new quay for seagoing vessels at Kanaaldok B2 in the Port of Antwerp. The company, based in Kallo, is demonstrating its in-depth expertise in port construction and quay wall structures. Thanks to careful preparatory work and close collaboration with specialist partners, the project is progressing fully to schedule.
Two established players join forces
Herbosch-Kiere formed a temporary joint venture with Hens NV specifically for this project. Project manager Hans Busschots explains: “Following a thorough financial and planning assessment, our joint tender was the only one selected. Work began in September 2025 and will continue until early 2027.”
Herbosch-Kiere is responsible for the civil engineering work, including installing a combi-wall further inland, the capping beam and the anchoring works. Site manager Jelle Cleys says: “We have built up extensive experience in this area and are a trusted partner of Port of Antwerp-Bruges. To avoid disrupting through shipping traffic, we are building the quay wall around 30 metres inland.”
Once the concrete work and wall anchoring are complete, Hens NV will demolish the old quay wall and carry out dredging works involving around 200,000 m³, depending on the available disposal site for the dredged material. “This sequence of work means the quay can be built in the dry. That is safer and more efficient than building on the site of the old quay,” says Cleys.


Specialist partners provide support
One of the key requirements in the specification was that the quay had to be installed using a leader-guided method. Busschots says: “This is a complex civil engineering operation that ensures a highly stable bank, able to withstand ship loads and earth and water pressure. That is why we worked closely from the outset with Gebr. van ’t Hek, a specialist subcontractor with the right expertise and equipment.”
“Because the site is in an area with heavy industry and a coal company operated there for many years, we took extra measures to prevent the existing contamination from spreading further,” adds Cleys. “Subcontractor Tjaden therefore connected a water treatment plant to the dewatering system. We also had a water-retaining screen (soil mix wall) installed in advance.”
A quay as a stepping stone to the future
This new quay will give the Port of Antwerp greater capacity. The project shows how technical expertise, tight planning and strong partnerships can deliver sustainable infrastructure. By building safely and efficiently inland, shipping can continue while the future takes shape. This project therefore strengthens not only the quay, but also the port’s position as an engine of growth and innovation.



Een zakelijke vraag aan Herbosch-Kiere? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering
- CompanyHerbosch-Kiere

















