Larger vessels to call at Ostend thanks to widened harbour entrance

The THV Jan De Nul-Soetaert-Smet F&C has been working hard since May last year to widen the harbour entrance…
To allow larger vessels to access the port of Ostend, the harbour entrance in the coastal city is currently being widened. Since May last year, the THV Jan De Nul-Soetaert-Smet F&C has been working hard to widen the entrance from 85 m to 125 or 145 m, moving the existing bank by around 40 m. The two sister companies are building a combined wall with an anchored capping beam and a new embankment.
The works are being carried out for the Maritime Access division of the Flemish Department of Mobility and Public Works. The access channel at the front of the Halve Maan site is being widened from 85 m to 125 m. At the rear, near the entrance to Visserijsluis, the channel is being widened to 145 m. Once the works are complete, the port will be accessible to vessels up to 200 m long, including larger jumbo ferries, cruise ships, cargo vessels and wind turbine installation vessels. The widening of the harbour entrance is part of the integrated plan for coastal protection and maritime access in Ostend. The plan aims to protect Ostend from flooding while strengthening the port’s economic position.

The access channel at the front of the Halve Maan site is being widened from 85 m to 125 m. At the rear, near the entrance to Visserijsluis, the channel is being widened to 145 m.
Combined wall and embankment
In the southern part of the project area, Jan De Nul-Soetaert is installing a combined wall. “The wall is made up of tubular piles, the largest of which have a diameter of 1700 mm and weigh 25 tonnes,” says Bert Vanmassenhove, project manager for the THV Jan De Nul-Soetaert. “They are topped by a capping beam 2.5 m wide and 3.7 m high. The 91 anchors, with a working load of up to 165 tonnes, were installed by Smet F&C, our partner in the THV. In the northern part of the project area, we are building a new embankment 175 m long. This involves moving 150,000 m3 of earth. The embankment is made up of mattresses and rock armour, with concrete HARO blocks as the top layer. There are more than 1,000 blocks, each weighing 15 tonnes. We are also strengthening the existing quay wall with 83 gravel columns extending to a depth of 14 m below ground level, installed from the water.”
Ahead of schedule
The scale of the work completed so far is clear. The new embankments, the combined wall with capping beam and the bank protection will be completed by the end of September. Over the coming months, Jan De Nul-Soetaert will carry out excavation work to establish a nature area in the zone east of the embankment. “The entire project will be completed by the end of this year, which puts us ahead of schedule,” says a proud Bert Vanmassenhove.

The top layer of the new embankment consists of concrete HARO blocks, each weighing no less than 15 tonnes.
Expertise and equipment in-house
Although the work is progressing smoothly, the technical challenges are considerable. “Tidal marine works are never easy,” explains Bert Vanmassenhove. “We are working on and around the water at the harbour entrance, where the wind has free rein. That makes us heavily dependent on the weather. Because of the weather conditions, we had to complete everything within an extremely short timeframe, between April and September. Another task that should not be underestimated was installing the concrete HARO blocks, each weighing no less than 15 tonnes. To avoid losing time and money, it is essential to keep working every day. Our great strength is that Jan De Nul and Soetaert have all the expertise and equipment needed in-house to complete projects like this successfully. Whether we need technical advice or more suitable equipment, it is all available at the touch of a button. We can effectively shop at Jan De Nul or Soetaert for everything we need. Thanks to this smooth collaboration, we have lost no time and the harbour entrance will even be ready ahead of schedule.”
Question about this story? Ask your question
Wie aan Verbreding havengeul ter hoogte van Halve Maan werkte
- grondankeractiviteitenSMET F&CMentioned in Ostend, De Halve Maan | Ground anchoring works on Halve Maandijk successfully completed
- waterbouwkundige en civiele werkenJan De Nul-SoetaertMentioned in Ostend, De Halve Maan | Ground anchoring works on Halve Maandijk successfully completed
- contractorTijdelijke Vereniging Jan De Nul: Soetaert: SmetMentioned in Works on Ostend harbour entrance channel completed
Keep following this
Get an email when a new story is published. No account needed.
- ProjectVerbreding havengeul ter hoogte van Halve Maan
- SubjectHydraulic engineering