Demeysluis back in service for shipping
Text DMOWImage Patrick Vanhopplinus - DMOW

The Demeysluis in Ostend has been back in operation for shipping since early June.
The renovation and modification work on its eight lock gates, which began in
2021, is now complete.
Following a three-year renovation project, vessels can once again enter the Port of Ostend via the Demeysluis. Repair work on the lock has been under way since October 2021. All eight lock gates have since been renovated. The contract was awarded for just over €3.5 million (excluding VAT). The Demeysluis connects the outer and inner harbours of Ostend and is more than 120 years old. The foundation stone was laid by King Leopold II on 19 June 1898. The lock is 123 metres long, 17.4 metres wide and 4.5 metres deep. It has eight gates in total: at each end, there are two ebb gates and two flood gates.

Final lock gates returned to service
In June, the final two renovated lock gates were installed in the Demeysluis. Early in the morning, a floating crane lifted them from Henri Deweertkaai, then carried them, suspended from a crane, to the lock. With each gate weighing more than 49 tonnes and measuring 12.5 m high by 11.6 m wide, the operation was carried out with care. Once transported to the lock, divers guided the gates onto their pintles, the underwater pivot points on which they rest. The gates were then connected at the top, via the collar, to the anchorage casting on the abutment. This operation was meticulously planned and took half a day for each gate. Over three days, the arms of both gates were connected to the hydraulic cylinders and the gates were electrically connected.
Yi-Bin Shan, Head of Maritime Access, Department of Mobility and Public Works: “We are pleased to have completed this challenging work and to have the lock back in operation. The Demeysluis is more than 120 years old, making its renovation an extremely complex challenge. Despite thorough preparation, we encountered several unexpected circumstances. Together with our partners, we resolved these challenges as quickly as possible to minimise disruption to shipping and port businesses.”

Renovation work at Henri Deweertkaai
The final two lock gates were removed from the lock in December 2023 and taken to Henri Deweertkaai for renovation. Oysters and silt were removed first. Repairs and modifications were then carried out on the steel structure, and the two gates were repainted.
The sluice valves and collar were also modified. The valves equalise the water levels on either side of the lock gate, allowing it to be opened so that vessels can enter the lock. The collar connects the lock gate to the anchorage casting on the abutment. Cathodic protection was also applied to the gates, and the seals were replaced.

Co-operation between the Flemish Government and the private sector
The painting and repair work on the lock gates was carried out for, and under the supervision of, the Maritime Access division of the Department of Mobility and Public Works. Maritime Access is responsible for constructing and maintaining the basic infrastructure in the Port of Ostend and ensuring that the port remains accessible to shipping. Tijdelijke Maatschap Hye, Demako, Oil, De Roeck carried out the work together with its subcontractors.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDemeysluis
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering