Two refurbished lock gates to be reinstalled at Demey Lock in Ostend

Today and tomorrow, two lock gates from Demey Lock will be brought back to the lock from Henri Deweertkaai. The gates, weighing over 65 tonnes and measuring 12.5 m high and 11.6 m wide, were lifted out of the gate chambers at the end of August 2022 for refurbishment. They are being transported towards the lock complex on a floating crane, before being reinstalled in the gate chambers. “This operation is part of the refurbishment works at Demey Lock, which have been under way since 2021. The final two lock gates will be lifted out of Demey Lock in December, after which refurbishment work on these gates will begin”, said Flemish Minister for Mobility and Public Works Lydia Peeters.
Demey Lock connects the outer and inner harbours of Ostend and is more than 120 years old. The foundation stone was laid on 19 June 1898 by King Leopold II. “The lock is 123 metres long, 17.4 metres wide and 4.5 metres deep. It has eight gates in total: each head has two ebb gates and two flood gates. Repair work at Demey Lock has been under way since October 2021. The works were awarded for just over €3.5 million, excluding VAT”, said Minister Peeters.

Complex operation
At around 9 am this morning, a lock gate was lifted from Henri Deweertkaai by a floating crane and then transported to Demey Lock, suspended from a crane. The gate arrived at Demey Lock at around 10 am. After being transported to the lock, the gate was lowered onto its pintle under the supervision of divers. This is the underwater pivot on which the gate rests. The top of the gate was then connected via the collar bracket to the anchorage casting on the abutment. The operation was meticulously planned. Tomorrow, the other lock gate will also be transported from Henri Deweertkaai to the lock complex. On Thursday and Friday, the arms of both gates will be connected to the hydraulic rams and the lock gates will be electrically connected.
The gates will pass through the Konterdam bridges after 9:00. This means the bridges will not need to open between 8 and 9 am, avoiding disruption to road traffic between Ostend and Bredene during the busy morning rush hour.

Refurbishment work at Henri Deweertkaai
These two lock gates were removed from the lock on 25 and 26 August 2022 and taken to Henri Deweertkaai for refurbishment. Oysters and silt were removed first. The steel structures were then repaired and modified, and the two gates were repainted. The sluices and collar brackets were also modified. The sluices allow the water level on either side of the lock gate to be equalised, after which the gate can be opened and vessels can enter the lock. The collar bracket connects the lock gate to the anchorage casting on the abutment. Cathodic protection was also applied to the gates and the rubber seals were replaced. Two more gates will be lifted out of the lock and taken to the quay for refurbishment in December.

Public-private partnership
The painting and repair work on the lock gates is being carried out on behalf of, and under the supervision of, the Maritime Access division of the Department of Mobility and Public Works. Maritime Access is responsible for constructing and maintaining the basic infrastructure in the port of Ostend and ensuring that the port remains accessible to shipping. Tijdelijke Maatschap Hye, Demako, Oil, De Roeck is carrying out the works together with its subcontractors Gardec, K&C Diving and Hebo. Several other divisions of the Department of Mobility and Public Works, the port of Ostend and various external parties are also involved, including CPC, Seco, SBE and Vandezande BVBA.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDemeysluis
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering