Demeysluis in Oostende reopens to shipping

Last two refurbished lock gates reinstalled in the lock
The Demeysluis in Oostende has been operational for shipping again since yesterday. The renovation and modification works on the eight gates of the Demeysluis, which began in 2021, have now been completed.
Following a three-year renovation project, vessels can once again enter the port of Oostende via the Demeysluis. Repair works on the Demeysluis have been under way since October 2021. All eight lock gates have been refurbished. The works were awarded for just over €3.5 million (excluding VAT).
The Demeysluis connects the outer and inner harbours of Oostende and is more than 120 years old. The foundation stone was laid on 19 June 1898 by King Leopold II. The lock is 123 metres long, 17.4 metres wide and 4.5 metres deep. It has eight gates in total: each lock head has two ebb gates and two flood gates.

Return of the last lock gates
Early last week, the last two lock gates were reinstalled in the Demeysluis after refurbishment. On Monday and Tuesday last week, the gates were lifted from the Henri Deweertkaai in the early hours using a floating crane, then transported to the Demeysluis suspended from a crane. Each of the two gates weighs over 49 tonnes and is 12.5 m high and 11.6 m wide. Once transported to the lock, the gates were lowered onto their pintles under the guidance of divers. The pintle is the underwater pivot on which the gate rests. The gates were then connected at the top, via the collar, to the anchoring casting on the lock abutment. This operation was meticulously planned and took half a day for each gate.
On Wednesday, Thursday and Friday, the arms of both gates were connected to the hydraulic cylinders and the gates were electrically connected. A final adjustment and check took place yesterday morning, after which the lock became operational again at around 12.00.

Yi-Bin Shan, Head of Maritime Access, Department of Mobility and Public Works: “We are pleased to have completed this challenging work and to have the lock operational again. The Demeysluis is more than 120 years old, which made the renovation a very complex challenge. Despite thorough preparation, we encountered several unforeseen circumstances. Together with our partners, we resolved these challenges as quickly as possible to minimise disruption to shipping and port businesses.”

Renovation works at the Henri Deweertkaai
The last two lock gates were removed from the lock in December 2023 and taken to the Henri Deweertkaai for renovation. Oysters and silt were removed first. Repair and modification works were then carried out on the steel structure, and the two gates were repainted. The sluices and collars were also modified. The sluices can be used to equalise the water level on either side of the gate, after which it can be opened to allow vessels to enter the lock. The collar is a component that connects the lock gate to the anchoring casting on the lock abutment. Cathodic protection was also applied to the gates, and the seals were replaced.

Collaboration between the Flemish Government and the private sector
The painting and repair works on the lock gates were carried out on behalf of and under the supervision of the Maritime Access Division of the Department of Mobility and Public Works. Maritime Access is responsible for constructing and maintaining the basic infrastructure in the port of Oostende and ensuring that the port remains accessible to shipping. The Hye, Demako, Oil, De Roeck joint venture carried out the works together with its subcontractors. Several other divisions of the Department of Mobility and Public Works, the port of Oostende and various external parties were also involved, including CPC, Seco, SBE and Vandezande BVBA.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDemeysluis
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering