K-Boringen and STADSBADER CONTRACTORS to build one of Belgium’s largest utility tunnels

K-Boringen, APK Group’s (micro)tunnelling division in Belgium, and STADSBADER CONTRACTORS are joining forces to build a new utility tunnel beneath the Visartsluis in Zeebrugge. The works, commissioned by the Flemish Government’s Department of Mobility and Public Works (MOW), will start in November and take two years. An information session for local residents will take place on 14 September.
Commissioned by the Maritime Access division of the Department of MOW, K-Boringen (APK Group) and STADSBADER CONTRACTORS will begin work on a new utility tunnel beneath the Visartsluis in November. The tunnel will bring all cables and pipes for electricity, gas, water and telecoms together underground. This will make the underground utilities easier to manage and more efficient, while making room for the port’s future development and growth.
Surface works to continue for two years
During the first year, STADSBADER CONTRACTORS will draw on its expertise in civil engineering to sink the shafts, with external diameters of 9.7 and 13.5 metres, to a depth of 36 metres.
The company has plenty of experience in shaft sinking. However, the depth and the associated challenges make this project a special one for them too. Pieterjan Pertz, Project Manager at STADSBADER CONTRACTORS: “Sinking shafts in stages to this depth is unprecedented in Belgium. The different soil layers we pass through each require a different approach. Thorough study and meticulous planning are therefore central to this project. We are confident that this project will once again have a positive impact on the Zeebrugge area.”
K-Boringen will then build the tunnel. At a depth of 30 metres, the company will construct the approximately 145-metre-long tunnel. With a diameter of 4.1 metres, the utility tunnel will be one of the deepest and largest in Belgium.
Ward Kerkhofs, managing director at K-Boringen, is looking forward to the technical complexity of the project and the benefits it will bring to Zeebrugge in the future. “With our expertise in microtunnelling, we can build this technically challenging utility tunnel with minimal impact on the surrounding area and port traffic. Projects like this require thorough technical preparation and close cooperation between all the partners involved.”
Once the tunnel has been built, the works will move on to phases 2 and 3. These will take place entirely underground and have minimal impact on the local area and its residents.