Hydraulic engineering

Waterworks at turning basin in Grobbendonk in full swing

In opdracht van De Vlaamse Waterweg voert waterbouwexpert Herbosch-Kiere momenteel werken uit langs het jaagpad aan het Albertkanaal in Grobbendonk.
In opdracht van De Vlaamse Waterweg voert waterbouwexpert Herbosch-Kiere momenteel werken uit langs het jaagpad aan het Albertkanaal in Grobbendonk.

Waterways construction specialist Herbosch-Kiere is currently carrying out works along the towpath on the Albert Canal in Grobbendonk, on behalf of De Vlaamse Waterweg. The turning basin is being significantly reduced in size, and a new quay wall and quay platform are among the structures being built. “A key aspect of this project is ensuring that water traffic serving the surrounding businesses can continue at all times,” says Jeroen Fransen, project manager at Herbosch-Kiere. The works are being carried out in phases, with the project expected to be completed in spring 2024.

For more than a century, Herbosch-Kiere has been building the infrastructure of today and tomorrow, in, on and alongside the water. Its work includes maintaining waterways, offshore energy projects, vessel salvage, providing foundations and remediating contaminated land. Herbosch-Kiere has successfully established itself as a waterways construction specialist, focusing on four strong pillars: civil engineering & water, maritime & offshore services, foundations and the environment. Herbosch-Kiere draws on many years of experience and specialist expertise in environmental and remediation works. In addition to carrying out remediation works, its specialities include developing and capping landfill sites.

The turning basin is being significantly reduced in size, and a new quay wall and quay platform are among the structures being built.

Traditional techniques

As a waterways construction specialist, Herbosch-Kiere is naturally a familiar sight on and alongside the Albert Canal. The company is currently hard at work in Grobbendonk. In short, the contract involves reducing the size of the turning basin and building a new quay wall downstream of the Grobbendonk bridge. This comprises an anchored sheet-pile wall with a capping beam and a quay platform for the existing quay wall. The works are being carried out for the benefit of the surrounding businesses Kerkstoel, Janssens-Smeets and Stadsbader. Jeroen Fransen says: “We are working both upstream and downstream of the turning basin, replacing the bank with a straight quay wall. Sheet piling, pile driving, anchors ... This project involves almost all the traditional techniques, which Herbosch-Kiere, of course, has mastered down to the last detail.”

Pouring the concrete quay wall.

Keeping water traffic moving

The turning basin itself is being substantially reduced in size. Jeroen Fransen says: “You could say it is being halved, from its current 80 m to 40 m once the works are complete. This will free up more land for the surrounding concessions. Work began in November 2022 and has been divided into three phases: the section downstream of the turning basin, the section upstream, and finally the turning basin itself. We are currently working downstream on the quay wall, and will then do the same upstream. You could certainly call this a standard job for us. But, of course, every project has its challenges. We have to ensure that water traffic can continue uninterrupted, and that loading and unloading at the quays can go ahead. That is why, for example, we have installed a temporary mooring facility.”

Waterways construction specialist Herbosch-Kiere is currently carrying out works along the towpath on the Albert Canal in Grobbendonk, on behalf of De Vlaamse Waterweg.

Clear communication

“This project is a perfect fit for Herbosch-Kiere, but surprises are always possible,” Jeroen Fransen continues. “After all, these are earthworks, and you never know what you might come across. Filling in the turning basin will also be a challenge. We are dealing with ground that has been continuously exposed to water for 50 years. Once the silt has been removed and the area filled in, the aim is to make optimum use of the new land. We have about six months for each of the three phases, although there will certainly be some overlap. We expect to complete the final section in early 2024. This is not only a project that suits us, but also one that brings Herbosch-Kiere’s strengths to the fore. We are demonstrating our knowledge and skills as a waterways construction specialist, as well as our experience in organisation, logistics and communication. We believe it is very important to be on the same page as all the parties involved, including the surrounding businesses.”     

Een zakelijke vraag aan Herbosch-Kiere? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeStrengthening waterways and coastlines
  • SubjectHydraulic engineering
  • CompanyHerbosch-Kiere
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.