Ongoing work continues while State Council ruling is awaited

At the beginning of December, the project team for the Nieuwe Sluis Zeebrugge complex project received two reports from the auditor of the Council of State. In 2019, several parties petitioned the Council of State to annul the preferred decision. This decision identifies the current Visartsluis as the preferred location for building the new sea lock in Zeebrugge. In both reports, the Council of State auditor recommends that the preferred decision be annulled. The Council of State’s final ruling will show whether or not it follows the auditor’s recommendations. In the meantime, the project is continuing its ongoing work, as it will be useful for the project’s future progress in any event. From a human perspective, it is also undesirable to halt this work.
Council of State proceedings
Jan Goemaere, chair of the task force: “It is too early to assume that all the hard work of the past year has been for nothing. Depending on the final ruling, there are several possibilities. We must wait for the ruling before making any statements ourselves. As communication is very important in this project, we have informed all affected residents, businesses and stakeholders, and explained clearly what this does and does not mean for the project. We will do the same when the ruling is handed down.”
Ongoing work will continue
In the meantime, the project team will continue its ongoing work. An analysis has shown that the outcomes of this work will be useful for the project’s future progress, whatever the Council of State’s ruling. It is also undesirable, from a human perspective, to halt this work. Five workstreams are currently under way:
- Integrated study: the ongoing studies will be completed. This study brings together all the technical studies on the construction and integration of the new lock.
- Property acquisition process for owners of homes within the new lock project perimeter: owners who were previously informed that their home lies within this perimeter and were given the opportunity to sell it voluntarily to the government ahead of schedule may still do so.
- Support process for businesses within the new lock project perimeter: the project liaison has already contacted all affected businesses about their specific situation.
- Liveability process: as part of this process, the project team is working with the local community to identify measures that can minimise disruption during and after the works. The project team would also still like to hear from residents about their concerns. The participation workshops planned for the spring will therefore still go ahead.
- Appointment of an area coordinator for Zeebrugge: the appointment process is currently under way. The role also covers more than just the Nieuwe Sluis Zeebrugge project.
Questions?
Do you have a question for the project team? Call the freephone information line on 0800 20 229 or email [email protected].
About the Nieuwe Sluis Zeebrugge complex project
Through the ‘Nieuwe Sluis Zeebrugge complex project’, the Flemish Government is preparing the port of Zeebrugge and its surrounding area for the future. The project has three pillars:
- a second access to the inner harbour;
- a new Nx connecting road to improve mobility;
- improved infrastructure and amenities to safeguard liveability in Zeebrugge.
The project will have a major impact on the surrounding area. That is why there is a strong focus on cooperation, dialogue and up-to-date information
More information
All the latest information about the project is available at www.nieuwesluiszeebrugge.be.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering