Hasselt’s Havenkwartier is getting a new, distinctive look, beautifully integrated into the city. The project includes an underground car park for 1,500 vehicles, 400 apartments and numerous hospitality and retail businesses. The district, also known as Quartier Bleu, is therefore undergoing a major transformation. Project manager Rob Eyckens talks about the project, which will give the site a significant upgrade.

Can you tell us more about the work you are carrying out?

Rob Eyckens: “We are installing the sewers and carrying out the foundation and paving works in the various streets and squares. We are also installing the stairways and undertaking the landscaping. In addition, we are responsible for building the access road to the underground car park and the associated emergency access ramp. In other words, Willemen Infra is carrying out all the external works.”

thumbnail2_300dpi-kopieren

The stylish natural stone gives the area a high-quality look.

What makes this project distinctive?

“What makes it so special is that all the paved areas are finished in natural stone, except for the concrete boulevard and the access road to the underground car park, which are surfaced with asphalt. The natural stone gives the area a more refined, stylish look. The pavements and side streets are made of special cobbles (Kandla Gres), which also give them an elegant appearance. We are laying 16,000 m² of these, which is a substantial amount for a project of this kind. The steps and kerbs are made of bluestone.”

Are you using any special techniques?

“For the external works above the underground car park, for example, it is essential to keep the load on the structure to a minimum. That is why we use Argex (fired clay pellets) as fill instead of sand. This requires a different approach, because ordinary site vehicles cannot drive over Argex pellets. We are also ensuring there is plenty of greenery throughout the site: we are planting no fewer than 187 trees. To give them the best possible growing conditions, we are installing underground tree pits made from plastic structures (40 m³ per tree) filled with growing medium. These pits keep the roots free from loading and allow the trees to grow well. Each tree is monitored individually and watered using a moisture sensor and a computer-controlled irrigation system.”

thumbnail3_300dpi-kopieren

The underground tree pits for the 187 trees.

How many people does Willemen Infra have working on site?

The site team consists of three site managers: Frans, Kenny and Joris, each with their own area of expertise. Kenny is mainly responsible for everything below ground: sewers and tree pits. Frans oversees the external works, while Joris is responsible for all the in-situ cast concrete structures. We are also building a 150 m-long, 3 m-high concrete retaining wall. This retains the soil so that the pavements above, which are 3 m higher than the adjacent Armand Herzstraat, can be built. The site team is also supported part-time by a surveyor, a work planner and an administrative assistant. Around 60 people on site, including our own staff, subcontractors, machine operators and drivers, give it their all every day.”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUsing and protecting the subsurface
  • SubjectHydraulic engineering
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.