Foundation engineering division gives water engineering specialist even greater strength

Foundations are crucial to every construction project. Drawing on its broad knowledge and expertise, the foundation engineering division at Herbosch-Kiere is always committed to achieving the best results. The project on the banks of the Scheldt in Wichelen was no exception. Commissioned by De Vlaamse Waterweg, Herbosch-Kiere strengthened the dike along a 2-kilometre stretch to prevent further erosion of the bank. “Having our own foundation engineering division at Herbosch-Kiere proved to be a major asset on this project too,” says ir. Marc Verlinden, Head of Foundation Engineering at Herbosch-Kiere.
For more than a century, Herbosch-Kiere has been building the infrastructure of today and tomorrow. In, on and alongside the water. Maintaining waterways, offshore energy projects, salvaging vessels, installing foundations, remediating contaminated land … Herbosch-Kiere has successfully established itself as a water engineering specialist, with a focus on four key pillars: civil engineering & water, maritime & offshore services, environment and foundations. In the latter field, Herbosch-Kiere draws on extensive experience in a range of foundation techniques, including diaphragm walls, micropiles, ground anchors and jet grouting.

Synergies
In 2016, water engineering specialist Herbosch-Kiere acquired foundation engineering company Fondedile. Since then, Herbosch-Kiere, and by extension the entire Eiffage Group, has had its own foundation engineering division. Marc Verlinden: “To create certain synergies, it was decided to fully integrate Fondedile into Herbosch-Kiere. The integration was a logical step in itself, as Fondedile was already based on the same site. We can also now draw on the group’s technical and administrative support, for example with studies, pricing, procurement and equipment. The foundation engineering division is now primarily active in the maritime sector, but other companies within the Eiffage Group can also call on us. That was the case, for example, when we installed diaphragm walls for a car park in Kortrijk as a subcontractor to the joint venture between Antwerpse Bouwwerken and Vuylsteke. We also remain available as foundation specialists to companies outside the group, offering them our expertise.”

Flexibility and efficiency
“We are keen to build on those synergies further,” adds Bavo Maekelbergh, site manager at Herbosch-Kiere. “It is a process of growth. All the companies in the group are, of course, aware of our activities, but the right projects also need to come along. We are really focused on larger projects. Ground anchors are our core business, but jet grouting, diaphragm walls and micropiles are also among our areas of expertise. In these fields, we can provide a very good service. One advantage is that we can respond very quickly and efficiently when it comes to studies, equipment and so on.”
“Our great strength is that we do not have to work as a subcontractor or depend on someone else’s schedule,” confirms Marc Verlinden. “The schedule is set from the outset, and within the group we can respond flexibly when needed. Herbosch-Kiere has made a deliberate choice to keep as many activities in-house as possible. For the client, that one-stop shop is a major asset.”

Scheldt bank, Wichelen
The project on the banks of the Scheldt in Wichelen is a good example of the added value of Herbosch-Kiere’s foundation engineering division. Alongside strengthening the dike, the flood defence was also raised. The stabilisation works form part of the Sigmaplan, through which the Flemish government aims to better protect Flanders against flooding. Marc Verlinden: “Steel sheet piles were installed in the bank to form a robust wall, with ground anchors providing additional stability. There are around 700 ground anchors in total. The slope on the river side was covered with armourstone so that water traffic could continue uninterrupted.”
Dredging was also carried out on the left bank. The dredged material was moved to the deeper zone on the right-hand side of the navigation channel, then covered with mattressing. The mattresses were subsequently covered with armourstone. Herbosch-Kiere’s full scope of works comprised stabilising the existing Scheldt bank over a length of 1,880 m, ensuring the flood defence met the Sigmaplan level of 8.00 m TAW, improving the public space alongside the flood defence near the social services centre in Wichelen, and building a pumping station and a new outfall sluice on the Bosbeek.
“Herbosch-Kiere handled the studies, anchor design, suitability tests and execution of the works. The space available for working between local residents’ back gardens and the water’s edge was limited, but we still managed to keep disruption to a minimum. That is always our aim, alongside zero tolerance on safety and a strong focus on sustainability and the environment,” concludes Bavo Maekelbergh.
Een zakelijke vraag aan Herbosch-Kiere? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering
- CompanyHerbosch-Kiere