Hydraulic engineering

Bridge dismantled in Zeebrugge becomes a quay in the Port of Ghent

Text Wouter Polspoel Beeld Artes Depret

Omdat de steiger 500 meter lang moest zijn, zodat de nieuwe generatie schepen er kunnen aanmeren, verlengde Artes Depret de voormalige brug met een vakwerkconstructie van 100 meter lang.
Omdat de steiger 500 meter lang moest zijn, zodat de nieuwe generatie schepen er kunnen aanmeren, verlengde Artes Depret de voormalige brug met een vakwerkconstructie van 100 meter lang.

A fine example of circular construction in infrastructure: Artes Depret has given a 400-metre-long bridge, dismantled in the Port of Zeebrugge two years ago, a second life as a quay in the Port of Ghent. The circular berth is due to become operational in September 2024, once the civil engineering works currently under way have been completed.

Two years ago, Artes Group dismantled the 400-metre-long so-called Verbindingsbrug in the Port of Zeebrugge to replace it with a brand-new bridge of the same length. The new bridge consists of two abutments and a 130-metre-long swing section. A swing bridge of this length is something of a rarity in Europe.

Artes Depret has given a 400-metre-long bridge, dismantled in the Port of Zeebrugge two years ago, a second life as a quay in the Port of Ghent.

Rather than treating the old bridge components as waste, Artes Depret recently gave them a second life as a berth in the Kluizendok in the Port of Ghent, after thorough sandblasting and a fresh coat of paint. The project was commissioned by Ghent Transport & Storage (GTS). The company is investing heavily in the Ghent petrochemical industry by building large storage tanks, and therefore needed additional loading and unloading capacity.

As the quay had to be 500 metres long to accommodate the new generation of vessels, Artes Depret extended the former bridge with a 100-metre-long truss structure. With its impressive scale, allowing as many as four vessels to berth at the same time, the new quay is undoubtedly a new landmark in the port. 

With its impressive scale, allowing as many as four vessels to berth at the same time, the new quay is undoubtedly a new landmark in the port.

Not the easiest option

By opting for reuse, Artes Depret certainly did not take the easiest route. Considerable preparation and study were required to ensure that the recovered bridge sections, transported by water to Ghent, met current standards and could be incorporated into a new structure. The contractor worked with Stranger Architects & Engineers on this.

Construction of the quay was completed in the spring, after work began in July 2023. The associated civil engineering works are in their final phase. The circular quay will be officially commissioned this autumn. 

Question about this story? Ask your question

Who worked on it

Aanlegsteiger Ghent Transport & Storage Gent in Gent

  1. contractorArtes Depret

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAanlegsteiger Ghent Transport & Storage Gent
  • ThemeExtending the life of bridges and tunnels
  • SubjectHydraulic engineering
  • CompanyArtes Depret
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.