Almost 1.5 million m³ dredged for new quay wall at Kanaaldok B2

A new quay wall was built at Antwerp’s Kanaaldok B2 on behalf of Havenbedrijf Antwerpen. At more than 800 m long, the quay wall, built by Jan De Nul Group, is the heaviest in Belgium and is designed for a water depth of up to 18 m.
Aertssen Group led the demolition of the old wall and, together with dredging specialist Ghent Dredging, took charge of the dredging works. “Thanks to Ghent Dredging’s expertise and know-how, we were able to complete this project successfully,” says Martijn De Groote, project manager at Aertssen Group.
Text | Niels Rouvrois Images | Aertssen Group / Ghent Dredging
The new quay wall means that larger ships with a deeper draught can now berth here. Aertssen Group and Ghent Dredging dredged the area between the old and new quay walls to a level of -12.5 m TAW. Along the full length of the quay wall, approximately 800 m, this involved removing no less than 1.4 million m³ of material. At the same time, the old quay wall was gradually demolished. “Our task involved precision excavation of the dry ground up to 50 m from the quay wall and dredging the underwater section,” explains Martijn De Groote. “The underwater section was already at -2 TAW and, like the land section, which was at +6 TAW, was dredged to -12.5 TAW.”
Aertssen Group carried out the contract in a temporary joint venture with Ghent Dredging. Martijn De Groote: “While Ghent Dredging focused mainly on the dredging, Aertssen took care of the dry section between the old and new quay walls. Half was excavated dry from the land, and the other half using pontoons from the water. Ghent Dredging also dredged the deeper layers between the old and new quay walls using its cutter suction dredger Quistreham. The whole operation was highly efficient.”

Aertssen Group led the demolition of the old wall and, together with dredging specialist Ghent Dredging, took charge of the dredging works.
Daddy Grizzly
The dredging works were carried out using a dredger, impressive excavators and Aertssen Group’s Yggdrasil pontoon. To carry out works on this scale, Aertssen Group brought in the Hitachi EX 1900, also known as Daddy Grizzly. The 270-tonne giant has a lifting capacity of 31 tonnes and is used to excavate the final layers at the deepest level. Martijn De Groote: “We used two large machines: the Hitachi 1200, both on land and on the pontoon, and Daddy Grizzly, because of its long reach. We deliberately chose to work with pontoons and cranes because much of the work had to be carried out close to the existing quay wall or between the existing sheet piles. Space was therefore limited.”
Sufficient manpower
Thanks to experience, the right people and a tight schedule, the project can be looked back on as a success. “We have the expertise in-house to carry out this kind of work properly. For this project, we would also like to highlight our excellent collaboration with Ghent Dredging. With its specialist know-how, Ghent Dredging was a strong partner. And, of course, there is also the commitment of our people. Having enough skilled staff is one of Aertssen Group’s great strengths. We used several teams on this project to ensure continuity and, where necessary, work day and night to keep to the schedule. As far as Aertssen Group is concerned, its work at Kanaaldok B2 is complete. Ghent Dredging will remain on site for a few more months to finish the final section. This means everything will be completed in line with the planned schedule,” concludes Martijn De Groote.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering