25 m vibro piles for quay wall extension in Port of Zeebrugge

25 m vibro piles for quay wall extension in Port of Zeebrugge

As the world’s largest car port, the Port of Zeebrugge continues to support its customers’ growth. To accommodate the expansion of International Car Operators, the Bastenakenkade in the Zuidelijk Kanaaldok is being extended by 1 km. A total of 910 vibro piles, each 25.25 m long, will help ensure the stability of the new quay wall.

Securing Zeebrugge’s leading position in the automotive sector: that is the goal behind the current construction work on the one missing section of quay wall in Zeebrugge’s outer harbour. The new quay will be 1,071 m long and will connect the Bastenakenkade to the return quay at the end of the dock, where International Car Operators’ head office is located. Extending the Bastenakenkade will provide more berths for ships, as well as around 30 ha of car storage space. On behalf of main contractor BESIX, piling contractor Soetaert is currently installing two rows of 455 vibro piles each.

foto-2-kopieren

The new piling rig was built at the depot in Oostende and then transported to Zeebrugge by water.

Converted leader rig

To resist the horizontal forces involved, all 910 vibro piles are driven into the ground at an angle of 14 degrees. In addition, a quay wall design requires pile foundations to be installed at considerable depth and through layers offering high resistance. The piles are therefore 25.25 m long. Erwin Dupont, head of the piling foundations division at Soetaert: “To reach the deeper founding levels, we had to use heavy piling equipment. That is why, together with our technical department, we converted the Liebherr HS895 leader crane in our fleet into a piling rig. By fitting it with our own lattice leader and a few other necessary components, we turned it into a PD rig.”

Transported by water

To avoid any risk, Soetaert built and tested the ‘new’ rig at its depot in Oostende before transporting it to Zeebrugge by water: “This saved us a lot of time, as we did not have to dismantle the rig and transport its various components separately. The rig arrived on site ready to go, which certainly helped us exceed our planned output after just 2 weeks.”

foto-1-kopieren

For the pile foundations of the new quay wall in Zeebrugge’s outer harbour, Soetaert converted a leader crane into a PD rig.

A remarkable team effort

Soetaert uses the IHC S90 hydroblock to drive the piles to depth. After the piles have been reinforced and concreted, the driving tubes are recovered using a ring vibrator. A pile extractor is also available on site, which can recover the tube with a pulling force of 400 tonnes in an emergency. All the piles are expected to be in place by the end of the summer holidays, after which Soetaert can start drilling around 15 km of strand anchors. Each is more than 50 m long and drilled at an angle of 45 degrees. “Given the exceptional depth at which we are working and the required pulling forces, this is certainly a special project for us. The smooth construction and commissioning of the PD rig is thanks to the close cooperation between our technical department, our in-house engineering department and the workers on site. For me, it is a remarkable team effort,” says Dupont.

A project to be proud of

Soetaert has been part of Jan De Nul Group since 2015. Dupont sees this as an asset on projects of this kind: “This contract clearly demonstrates how Soetaert and Jan De Nul have all the techniques required to build a quay wall in-house. While we take care of the foundation works, Jan De Nul can handle all the concrete works. We can also use our 60 m leader to install even longer vibro piles. That opens up opportunities for other projects at home and abroad.”      

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeStrengthening waterways and coastlines
  • SubjectHydraulic engineering
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.