Sewerage & underground infrastructure
Parking moves underground at Gedempte Zuiderdokken

The transformation of Gedempte Zuiderdokken in Antwerp is gathering pace. The parking spaces are moving underground to make way for an expansive urban park: Dok Zuid.
The first underground car park, Steendok, has just been completed by Van Laere. Next up is Kooldok car park. Both car parks are being built within the existing dock walls, a challenge Van Laere is happy to take on.
Het Zuid is now a leading district in Antwerp, while Gedempte Zuiderdokken is best known as a grey parking area. Dok Zuid will change that for good. The first step towards creating the park is to move the car parks underground. They will be located entirely within the dock walls of the former Kooldok and Steendok. Together, they will provide around 2,000 parking spaces for cars and around 300 for bicycles. The top 1.5 m of the docks was demolished when they were filled in, but the rest has been well preserved and will once again be visible from the first underground level of the car parks.
The first car park, Parking Steendok, officially opened in December. Van Laere began the preparatory works in November 2017, on behalf of operator Q-Park Belgium nv, but the project was delayed by a legal dispute with local residents over the design. Van Laere was able to resume work in December last year and, despite a temporary suspension due to coronavirus in the spring, the construction company completed the first car park before the end of the year. Van Laere will now start building Kooldok car park, which is due to be ready in spring 2022.

Old docks
Each car park has four underground levels and is built from precast concrete. Their location within the existing dock walls presented a number of challenges. “When the docks were filled in in 1969, they were filled with sand and the old dock bed was not dredged. The coping stones that had been on the quay walls also ended up in the old docks. We had to excavate all of this before we could construct our cofferdam,” explains Thomas Quirynen, project manager at Van Laere.
Diaphragm walls
The car park is being built in a closed excavation pit, using diaphragm walls and a precast concrete structure. Thomas Quirynen explains: “The diaphragm walls start on level -1 so that the old dock walls remain visible on this level. They extend down into the Boom clay, effectively creating a ‘watertight box’. In certain places, specifically where the stairwells are located, the diaphragm walls pass through the dock walls, so we had to remove the dock walls at those points. Once the diaphragm walls were complete, we could continue excavating and install the ground anchors that stabilise them. As soon as we had reached the required depth, we constructed the foundation strips on which the entire building rests. We could then start building upwards with the precast structure.”
To avoid installing a second row of deeper anchors and the associated heavier dewatering, a layer of soil had to be left temporarily in place on level -4 to provide additional support for the diaphragm walls, until the floor topping slabs had been poured. As a result, this soil could only be removed once the precast structure was in place. Van Laere did this by excavating the soil through two openings from ground level, using cranes fitted with modified excavator arms.

Unique roof structure
Van Laere also built the car park itself in precast concrete and installed the building services. “One particular challenge was that we could not use a conventional hollow-core slab for the roof structure, because it would not have had sufficient load-bearing capacity for the park being built above it. We designed a special type of beam for the job, which was manufactured by our precast concrete partner Ergon. The beam can easily carry the heavy soil load, even with spans of up to 15 m,” says Thomas Quirynen.
Extensive experience
“The combination of civil engineering works, finishing and building services makes this a very engaging project to work on. Thanks to our dedicated staff and extensive experience in building underground car parks, we have successfully completed the first phase of this project,” concludes a satisfied project manager. On to the next car park!
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUsing and protecting the subsurface
- SubjectSewerage & underground infrastructure