New final settlement tanks taking shape at Lichtaart WWTP
Text Niels Rouvrois Beeld Colas

The wastewater treatment plant (WWTP) in Lichtaart, built in 1981, is currently undergoing a major renovation. Given the size of its catchment area and the applicable discharge standards, the plant was due for an upgrade. As part of the project, Colas is responsible for constructing two new final settlement tanks. “Given the complexity, this is certainly a fine example of skilled workmanship,” says Anja Eeckhout, operations manager for civil engineering at Colas.

The upgraded and expanded WWTP will be able to treat the wastewater from 41,000 residents biologically. This means that up to 2,636 m³ of wastewater per hour will flow into the plant, more than the volume of a 50-metre Olympic swimming pool every hour. To achieve this, an additional supply pipeline must also be laid to the plant. After treatment, the water flows into the Grote Calie (Caliebeek).
Second tank under construction
At the end of October, the base slab of the first final settlement tank at the wastewater treatment plant was poured in concrete, marking significant progress in the transformation of this essential infrastructure. Construction of the second final settlement tank also began in May. Anja Eeckhout: “The first tank was built on a new site, allowing the three old tanks to remain in operation. The new tank is now operational, so three tanks can continue running while one of the old tanks is demolished. The second new tank is now being built on that site. To ensure that wastewater treatment and supply could continue uninterrupted, it was, of course, vital to keep three tanks operational at all times.”

While the electromechanical renovation is being carried out by another contractor under a separate tender package, Colas is responsible for all civil engineering works. Anja Eeckhout: “Concrete works, pipelines, sewers, aeration, final settlement tanks … they are all part of our scope. It is crucial to work in phases. For example, the new aeration system has to be commissioned before the old one can be dismantled. This project therefore calls for a great deal of preparation and planning. The civil engineering and electromechanical works also need to be closely coordinated.”
Complexity
Keeping the plant as a whole operational is not the only challenge facing Colas on this project. The need to meet very strict ground flatness tolerances is also far from straightforward. The complexity lies in combining a circular tank with a sloping floor. A metal screed was therefore used to determine the correct finished floor level, which is essential for the tank’s operation, as the scraper arm must be able to rotate across the floor.

Anja Eeckhout: “This is a structure that certainly requires a high level of skill. The flatness of the ground was a key consideration. The scraper arm needs to move with near-millimetre precision. The floor could not have any bumps or dips. We therefore developed our own site screed to get the floor to exactly the right level. Positioning the tank’s 4-metre-high walls while taking account of the sloping base was also a challenge. This is certainly a fine example of skilled workmanship.”
It goes without saying that this project is more challenging than the standard projects Colas typically undertakes. “But the quality of the work shows that we are the right partner for this project. A complex project like this always takes some figuring out at the outset, but thanks to thorough preparation and the knowledge and experience we have in-house, we are so far delivering the project to the client’s satisfaction. We expect to complete the second final settlement tank by spring 2025. Once the second new tank is operational, the next old tank will also be demolished. The third old tank, which is newer than the other two, will remain in operation for now and will not be replaced,” concludes Anja Eeckhout.
Question about this story? Ask your question
Wie aan RWZI Lichtaart werkte
- burgerlijke bouwkundewerkenColasIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRWZI Lichtaart
- SubjectSewerage & underground infrastructure
- CompanyColas