Sewerage & underground infrastructure
Fluvius strengthens Dendermonde’s networks for the energy transition

Grid operator Fluvius is pressing ahead with the modernisation of the electricity network in Dendermonde. The project aims to ensure a reliable and efficient network that meets the growing energy needs of the bustling city centre. By laying high-capacity cables and building a switching station, Fluvius is also working hard on the networks of the future in the Ros Beiaard city. The works began at the end of February and will continue until this summer.

Electricity network upgrade
The project involves building a new switching station on the outskirts of Dendermonde and modernising the electricity network in the city centre. The existing 230 V network in the central streets is still working well, but it will not be sufficient in the future, when there will be many more electric cars, heat pumps and solar panels. Fluvius is therefore laying additional medium- and low-voltage networks, from Vlasmarkt via Brusselsestraat to Geldroplaan.
The new switching station is located on the corner of Zuidlaan and Geldroplaan. It replaces the existing switching station on Vlasmarkt, which had become outdated. The old switching station is being converted into a modern remotely controlled distribution substation to supply the local low-voltage network.

Minimal disruption and open communication
Fluvius is coordinating its work with other utility companies, such as Proximus and Wyre, so that they can lay their own cables in the same trench. This means the pavement only has to be opened once, causing less disruption for residents.
The grid operator is also seeking to limit disruption by carrying out the work in several phases. These works have a major impact on the city centre, so a great deal of emphasis is being placed on tight scheduling and open communication. Residents were invited to a general information session, and the information kiosk is still open to everyone. The project also includes a clear traffic management plan to regulate traffic flows and ensure safety.

The project is currently on schedule, with the aim of completing the works by the start of the 2024 summer construction holiday. Fluvius emphasises the importance of thorough preparation and cooperation with all parties involved to meet Dendermonde’s energy needs, both now and in the future.
More information about the works and phasing is available on the information page on the Dendermonde city website: www.dendermonde.be/werkenfluviuscentrum
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeRenewing pipelines and sewers
- SubjectSewerage & underground infrastructure