Fluvius gives Asse’s electricity network a major upgrade

Almost all utility lines in the centre of Asse are currently undergoing a major overhaul. As part of the energy transition, grid operator Fluvius is using these works to strengthen the electricity network in Asse step by step and make it fit for the future. Work near the town hall has now been completed. All works in the centre are due to be finished by early 2026.
One of the main reasons for the utility works in Asse was a series of water leaks in the centre. These are clear signs that the local water mains were in urgent need of renewal. To avoid having to dig up roads and pavements several times, other utility companies also joined the project to renew the energy and telecoms networks at the same time.
To make this huge project manageable, Fluvius and water company Farys are sharing the workload. Fluvius is taking charge of half the works along the N9, while Farys is managing the works from Nieuwstraat onwards. This cooperation between utility companies is crucial to keeping disruption to a minimum for everyone in Asse.

Works proceeding as planned
New pipes have already been laid along both sides of the N9, between Asse station and the town hall. The adjacent homes are now being connected to the new cables and pipes. From the summer, work will move to Steenweg, Nieuwstraat, Kalkoven and Nerviërsstraat. Everything is on track for completion by early 2026.
Stronger medium- and low-voltage networks and new and upgraded substations
In line with the planned phasing of the utility works, Fluvius is completely renewing and strengthening the medium-voltage electricity network. Each such network supplies electricity to more than a thousand households. The low-voltage electricity network is also being strengthened. These are the cables that run to homes. Sections of the 230-volt network will be supplemented throughout with stronger 400-volt cables.

These upgrades are planned for Stationstraat, Weverstraat, Steenweg, Kalkoven, Nerviërsstraat, Nieuwstraat and Edingsesteenweg. Further network reinforcement works are planned in the wider area around the centre of Asse during 2026, specifically to install 400-volt cables.
As well as electricity cables, Fluvius is also upgrading several substations along the route. The old distribution substation on Stationsplein is being completely replaced. These improvements will ensure that the centre of Asse is ready for the energy transition and the arrival of many more electric vehicles, solar panels and heat pumps.
More information about the utility works in Asse?
Visit Utility works in Asse centre: Municipality of Asse
Question about this story? Ask your question