Fluvius is currently carrying out major grid reinforcement works in and around Aalst. This requires high-voltage cables to be laid from the Aalst transformer station in Erembodegem, including beneath the E40. The works are being carried out in preparation for several major business connections. At the same time, Fluvius is renewing and reinforcing the existing local electricity grid in readiness for the energy transition. All the works will be completed by the end of this summer.

Major investments require a lot of energy

Two companies in the Aalst region are planning major investments that will require a great deal of energy: just under 20 MW (megawatts) in the first phase and 30 MW in the longer term. One of these companies is LCL Data Centers, which is building a state-of-the-art data centre, LCL Brussels-West, in Erembodegem (Aalst). This will add to the company’s 4 existing data centres in Antwerp, Huizingen, Gembloux and Diegem (head office). The new site has been designed with future capacity and power requirements in mind, as well as with special facilities for major cloud providers and other large-scale customers. Fluvius is also laying new fibre-optic cables for LCL.

Michel Neckebroek, Head of Networks at Fluvius in the Aalst region: “We are combining the business connections with renewal works on our electricity grid. Three high-voltage cables run from the Aalst transformer station in Erembodegem to each of the two companies concerned. They share a trench with our other electricity cables, running along municipal and regional roads and then through the centre of Aalst, over a total distance of around 8 kilometres. To minimise disruption, we are also giving our grid a major upgrade. We are replacing all the old cables and installing 400-volt cables wherever we open up the pavement. This will make the energy supply fit for the future, when much of the energy currently provided by fossil fuels will come from electricity.”

Security of supply and deadlines

Herwig Laleman, account manager for major business customers at Fluvius: “These companies are investing heavily in the region, so it is very important that the planned schedule is met. And it will be: we are on track to meet all the deadlines. We are providing these customer connections with redundancy, using multiple cables. This means we can continue to supply the contractually agreed capacity even if one of the cables fails. We can therefore offer these customers maximum security of supply, which is also what we strive to provide to all households in Flanders.” ​

Minimal disruption

The cable route runs through the centre of Aalst. However, by dividing the installation works into several smaller projects and thanks to close cooperation with the city, the works can be carried out without major disruption to traffic.

The project in figures

  • 24 km of ‘PRC 400’ cables (renewal of the existing electricity grid)
  • 1,500 metres of ‘PRC 95’ cables
  • 13 km of ‘PRC 150’ cables
  • 80 km of PRC 240 (cables laid specifically for the two business connections)
  • 20 km of low-voltage cables
  • Directional drilling beneath the E40 near Aalst

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectLCL Brussels-West
  • ThemeRenewing pipelines and sewers
  • SubjectSewerage & underground infrastructure
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.