Dewatering with a focus on minimising environmental impact

De uitvoering van de bemaling voor de aanleg van de riolering moet zo uitgevoerd worden dat de impact hiervan op het natuurgebied minimaal is.
De uitvoering van de bemaling voor de aanleg van de riolering moet zo uitgevoerd worden dat de impact hiervan op het natuurgebied minimaal is.

Kampenhout Municipality and Aquafin plan to install and commission a separate sewerage system in the Terbronnen district of Kampenhout. The new foul-water sewer installed by Kampenhout Municipality in the district will connect to the wastewater treatment infrastructure via a collector sewer to be installed by Aquafin in Kasteellaan, near the Keibeek. This will ensure that wastewater is ultimately conveyed to Kampenhout wastewater treatment plant. G. Smeyers of Zandhoven is responsible for the specialist dewatering work on this project.

Rainwater will be collected throughout the district in a separate pipe and discharged into the Keibeek. Work began in early June 2022 and is expected to take just over a year. The tender specifications paid particular attention to the dewatering works, to ensure compliance with the strict requirements of the dewatering permit. The permit stipulated that the daily dewatering rate must not exceed 980 m³/day in the protected nature area and 1,685 m³/day in the surrounding zones. The total permitted annual volume was 150,200 m³/year.  

Horizontal drains

The dewatering for the sewer installation must be carried out in a way that minimises its impact on the nature area. To limit the volume of water pumped, the tender specifications required the use of horizontal drains. This method was explicitly specified following positive experience with the same dewatering technique on work carried out nearby. All dewatering pumps must also be controlled automatically to prevent the groundwater level from being lowered unnecessarily. Dewatering must be operational for as short a time as possible, and the length of each dewatering line must not exceed 30m in the nature area or 50m in the surrounding zones. 

G. Smeyers of Zandhoven is responsible for the specialist dewatering work on this project.

Reinfiltration

Finally, the installed drains must also be used after the sewer has been laid to reinfiltrate as much of the pumped groundwater as possible back into the ground. Given the strict conditions of the dewatering permit and the complex subsurface, where peat and sandstone layers may be encountered, this is certainly no routine dewatering job. Viabuild called on the services, expertise and know-how of G. Smeyers, specialists in complex dewatering, to carry out the work.  

Work on the first phase began in early June 2022, with horizontal drains being installed at a depth of 5m. A surprisingly large number of hard sandstone layers were encountered underground. Work therefore had to be stopped quite quickly to prevent serious damage to the drainage machine. During an urgent meeting between all parties involved, G. Smeyers proposed an alternative method using mechanically drilled vertical wellpoints, designed so they could be converted into infiltration wells after the dewatering phase. 

Storage tank

Two additional drains are being installed at the bottom of the trench. After the sewer has been laid, these will also be used to infiltrate dewatering water. While the sewer is being installed, the pumped water is collected in a storage tank before being discharged into the Keibeek. At the client’s request, the tank has been fitted with the necessary connections to allow water to be drawn off.

During the current period of severe drought, people are making grateful use of the opportunity to collect this water free of charge. On site, it is used to spray the streets and site roads to keep dust down. The municipal services are also drawing water to irrigate their own green spaces, while several local residents are making use of the free water to water their gardens and fill their rainwater tanks. 

Thanks to the ingenuity of G. Smeyers, a solution was quickly proposed that allowed work to continue without interruption while still meeting the permit requirements.     

Een zakelijke vraag aan Smeyers nv? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUsing and protecting the subsurface
  • SubjectSewerage & underground infrastructure
  • CompanySmeyers nv
  • CompanyViabuild
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.