Sewerage & underground infrastructure

Challenging sewer renovation using shell sections in Mechelen

Text Renotec / Niels RouvroisImage Renotec

Voor de renovatie van de riolering, een oude vliet, werkte het team met schaaldelen.
Voor de renovatie van de riolering, een oude vliet, werkte het team met schaaldelen.

One of the most important sewers in Mechelen was in urgent need of renovation. It was no easy task, but Renotec took it on for Pidpa, the sewer manager for the City of Mechelen. What looked like a minor subsidence on Guido Gezellelaan in February 2022 turned out to be more serious. When the ground was excavated, part of the sewer collapsed. Renovating the 300-metre-long sewer, 4 metres underground, was expected to take months.

One of the most important sewers in Mechelen was in urgent need of renovation.

Major works underground

The sewer in question carries wastewater from almost half of the residents in the city centre. If a problem arises in this sewer, it is vital to respond quickly and flexibly. “And that’s something we can do,” says Danny Roelants, project manager at Renotec. “Sewer renovation in urban environments is becoming increasingly challenging, but our people specialise in every possible pipe-laying technique and know how to deal with unforeseen circumstances. In Mechelen, there had been some minor subsidence next to an inspection chamber. Normally, that would be a job of just a few days at most. But when the workers started digging, they found that the sewer was in very poor condition. During excavation, the roof of part of the sewer collapsed.”

The street at Groot Begijnhof was closed to through traffic until the end of March 2023. “That’s difficult for residents and passers-by,” project manager Stijn Gielis continues. “Minimising disruption remains our aim. Keeping a road open for days or weeks to carry out work is a thing of the past, but we still need to be able to do our job. We also needed space to manoeuvre the large components required for the renovation. We were able to set up a spacious, easily accessible work pit on site fairly quickly. The residents had no idea just how much work we were carrying out there.”

A shell section is made of glass fibre-reinforced plastic and can be inserted into the sewer to create a completely new sewer without holes or subsidence.

Innovative shell-section installation

The team used shell sections to renovate the sewer, an old watercourse. Made of glass fibre-reinforced plastic, these sections can be inserted into the sewer to create a completely new sewer without holes or subsidence. The largest shell sections weigh 950 kilograms, and the smallest 450 kilograms. 

“Using another method, we would have had to dig up the entire street,” Danny explains. “That is barely feasible in cities nowadays. The work would also have taken much longer. We developed our own innovative equipment to move and secure the shell sections. We installed an average of 3 to 4 sections a day. At the same time, and as a precaution, we replaced all the household connections, as a survey had identified defects.”

Rain had already disrupted the work once. To keep the sewer as dry as possible, a dam was installed underground so that the water could be pumped out. Stijn says: “Our people were always on their toes, especially because of the household connections. If one of the neighbours flushed something down the toilet, we knew about it …” 

A template was made to determine the most suitable size of shell sections.

Renovated for the future

The outcome is now positive. The work has been completed in full. There is no doubt that the investment of approximately 1.2 million euros will pay off. The renovated sewer will last at least 50 years, and the shell-section technique used here has delivered a sustainable solution. Sprayed concrete could also have been used to resolve the problem quickly. But from a sustainability perspective, shell sections are a much more attractive option. 

“We are constantly looking for sustainable techniques, so that we can then apply them safely and to the highest professional standards. The future looks bright for the residents of Guido Gezellelaan. The sewer and household connections have been expertly renovated for the long term. Thanks to our heroes, who worked in the pit here every day,” Danny concludes.

Pidpa manages 5,000 kilometres of sewer network in 46 municipalities in Antwerp province as an integrated water company. It regularly calls on reliable partners such as Renotec, whose work adds value to this management.     

“We developed our own innovative equipment to move and secure the shell sections.”

■

Question about this story? Ask your question

Who worked on it

Rioolrenovatie Pidpa Mechelen in Mechelen, renovatie

  1. rioolbeheerderPidpa

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRioolrenovatie Pidpa Mechelen
  • ThemeRenewing pipelines and sewers
  • SubjectSewerage & underground infrastructure
  • CompanyPidpa
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.