Sewerage & underground infrastructure

Challenging concrete renovation at Pierre Vandammesluis

“We optimaliseren onze werkprocessen continu en konden zo bepaalde toepassingen efficiënter maken.”
“We optimaliseren onze werkprocessen continu en konden zo bepaalde toepassingen efficiënter maken.”

Since 2010, continuous structural renovation work has been carried out on behalf of the Department of Mobility and Public Works, Maritime Access, at Pierre Vandammesluis. At 500 m long, 57 m wide and up to 18.5 m deep, it is the largest lock in the Port of Zeebrugge.

Renotec is currently carrying out renovation work on the bridge chambers, covering everything from start to finish: cleaning walls and carrying out injection work, through to concrete repairs and applying a coating.

Pierre Vandammesluis connects the outer and inner harbours and is therefore crucial to ensuring the future accessibility of the inner harbour in Zeebrugge. After 30 years, the lock was due for a complete overhaul. Renotec’s concrete repair division is renovating the various bridge chambers. “We clean and inspect the walls, carry out injection work and concrete repairs, and apply a protective cement-based coating,” Renotec says. “Some of these concrete repairs are carried out manually, but most are done using the sprayed concrete method. We are carrying out all this work throughout the bridge chambers, sometimes at depths of up to 25 m. In total, 12,000 m² is being cleaned and more than 9,000 m² coated. Concrete repairs cover an area of 600 m² and use 108,000 kg of repair mortar, while 7,260 galvanic sacrificial anodes and several monitoring boxes are being installed.”

The project’s main challenge is its unique location.

The concrete was cleaned by grit blasting. Damage to the concrete was assessed both visually and by sounding. Renotec explains: “The ‘unsound’ concrete was removed down to the non-carbonated concrete, but because of the presence of chlorides, concrete also had to be removed to a depth of 1 cm behind the reinforcement. This resulted in an average removal depth of 10 cm. Another recurring problem was water ingress through the old construction joints. These areas were injected to ensure effective concrete repairs. Because of the chlorides and to counter the ring-anode effect, galvanic sacrificial anodes were attached to the reinforcement. Some of the sacrificial anodes are being monitored so their service life can be tracked over the coming years. The areas are then repaired with repair mortar, and everything is cleaned once more before the protective coating is finally applied.”

A unique site

The project’s main challenge is its unique location. Renotec explains: “The bridge continues to move during the works, so its counterweight moves inside the bridge chamber. The entire site setup has therefore been designed to keep everyone out of the danger zone created by this movement, allowing work to be carried out 100 % safely. There are only two openings, each measuring 1 by 6 m, through which all the materials have to pass. The openings are accessible only when the bridge is raised, and can be used when it remains raised for an extended period, as vertical transport is carried out by crane to a depth of 25 m. These closure periods last a maximum of 4 to 5 hours and must be kept to a minimum to reduce the impact on shipping. Not only our materials, but also the waste generated during the repair work has to be removed through the small openings. Since big bags will not fit through, we made custom wooden crates.”

Renotec’s concrete repair division is renovating the various bridge chambers at Pierre Vandammesluis

Rope access technicians

The scaffolding was erected between bridge movements. Everyone therefore had to leave the chamber whenever the bridge moved. Renotec explains: “We also had to make sure that nothing was in the way. In addition, we had to take account of certain areas where the bridge’s counterweight passes. This work could only be carried out during closure periods, when the bridge was closed. We brought in rope access technicians, who abseiled down the walls of Pierre Vandammesluis to reach the inaccessible areas. We also used a spider lift, the only machine that would fit through the opening.”

In total, 12,000 m² is being cleaned and more than 9,000 m² coated.

Adaptability

For both Renotec’s tradespeople and its site management team, this is a unique project. “Fortunately, a true Renotec professional is adaptable and innovative,” the company says. “This enables us to respond quickly to unforeseen circumstances. We also consistently apply lean principles. We aim to deliver a high-quality result through efficiency, preparation and common sense. We continuously optimise our work processes and have been able to make certain applications more efficient. The first bridge chamber renovation took 6 months. The last 2 bridge chambers were renovated simultaneously in 2.5 months. A wonderful result, thanks to all the tradespeople and site managers involved.”     

Question about this story? Ask your question

Wie aan Pierre Vandammesluis werkte

  1. main contractorTHV Soetaert-Jan De NulMentioned in Pierre Vandammesluis na grondige renovatie weer klaar voor gebruik
  2. engineering consultancySBEMentioned in Pierre Vandammesluis na grondige renovatie weer klaar voor gebruik
  3. hijsschipRambizMentioned in Pierre Vandammesluis na grondige renovatie weer klaar voor gebruik
  4. contractorJan De Nul GroupMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  5. contractorSoetaertMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  6. contractorAlmexMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  7. contractorDemakoMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  8. clientDepartement Mobiliteit en Openbare WerkenMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  9. engineering consultancystudiebureau SBEMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  10. renovatiewerkenRenotecIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPierre Vandammesluis
  • ThemeStrengthening waterways and coastlines
  • SubjectSewerage & underground infrastructure
  • CompanyRenotec
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.