Impressive works at the Pierre Vandammesluis in Zeebrugge

Impressive works at the Pierre Vandammesluis in Zeebrugge

Today, a lock gate at the Pierre Vandammesluis in the port of Zeebrugge was impressively transported from the outer harbour back to the lock. After a year and a half of refurbishment, the gate, weighing over 2,000 tonnes and measuring 60 m long, 24 m high and 11 m wide, was transported towards the lock complex by a floating sheerleg and then installed in the gate chamber. The operation is part of the major refurbishment works at the Pierre Vandammesluis, the crucial access route to Zeebrugge’s outer harbour.

Refurbished lock gate reinstalled

20211206, Belgium, Zeebrugge, Reinstallation of Pierre Vandammesluis 20211206090034 ID/ ID/ PHOTO AGENCY

Meticulous preparation

Transporting the lock gate from the outer harbour to the gate chamber is a large-scale, complex operation involving around 50 people. The entire lifting operation was meticulously prepared over several weeks and is expected to take 13 to 14 hours. The weather must also be taken into account. The operation cannot go ahead if visibility is too poor or the wind is too strong. The gate was transported from the outer harbour using the floating sheerleg ‘Rambiz’, which can lift a weight of 3,300 tonnes. 

20211206 – Belgium – Zeebrugge – Terugplaatsing Pierre Vandammesluis 20211206081036 ID/ ID/ PHOTO AGENCY

Major maintenance works in the outer harbour

Over the past year and a half, this lock gate has undergone a major refurbishment at the ICO terminal in the outer harbour. Oysters and silt were removed first. The contractor then replaced several mechanical components and installed new equipment, including a compressor, an airlift and 6 agitator propellers. Several modifications were also made to the steel structure, including the installation of four additional butterfly valves. Finally, the gate was repainted to protect it against corrosion. As the work was being carried out on the site of a vehicle terminal full of new cars, every effort was made to minimise disruption to the operator. For example, the gate was completely wrapped in plastic sheeting during blasting and painting to prevent abrasive grit from escaping and potentially damaging the parked cars.  

20211206 – Belgium – Zeebrugge – Terugplaatsing Pierre Vandammesluis 20211206085547 ID/ ID/ PHOTO AGENCY

€120 million refurbishment

Flemish Minister for Mobility and Public Works Lydia Peeters emphasises the importance of the works: “The port of Zeebrugge is an important maritime hub and an economic engine for Flanders. The Vandammesluis is currently the only access route to Zeebrugge’s outer harbour. It is the Flemish Government’s responsibility to ensure the port remains accessible. Flanders is making over €24 million available for the refurbishment of this gate. We are investing a total of €120 million in the complete refurbishment of the lock.”

20211206 – Belgium – Zeebrugge – Terugplaatsing Pierre Vandammesluis 20211206085418 ID/ ID/ PHOTO AGENCY

Structural refurbishment works at the Pierre Vandammesluis have been ongoing since 2010. This is the second time this operation has taken place in Zeebrugge. The outermost lock gate was disconnected in 2018, refurbished in the outer harbour and then reinstalled in 2019. The innermost gate was lifted out of the water in May last year and has now been brought back. At least one more inner gate, together with its guide rails, will be refurbished in the coming years. This gate will remain in the gate chamber during the refurbishment and will therefore not be disconnected.

Question about this story? Ask your question

Wie aan Pierre Vandammesluis werkte

  1. main contractorTHV Soetaert-Jan De NulMentioned in Pierre Vandammesluis na grondige renovatie weer klaar voor gebruik
  2. engineering consultancySBEMentioned in Pierre Vandammesluis na grondige renovatie weer klaar voor gebruik
  3. hijsschipRambizMentioned in Pierre Vandammesluis na grondige renovatie weer klaar voor gebruik
  4. contractorJan De Nul GroupMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  5. contractorSoetaertMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  6. contractorAlmexMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  7. contractorDemakoMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  8. clientDepartement Mobiliteit en Openbare WerkenMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  9. engineering consultancystudiebureau SBEMentioned in Images of spectacular operation at Pierre Vandammesluis in Zeebrugge
  10. renovatiewerkenRenotecMentioned in Challenging concrete renovation at Pierre Vandammesluis

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPierre Vandammesluis
  • ThemeStrengthening waterways and coastlines
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.