Ronse gets a ‘future-proof’ electricity grid

Ronse gets a ‘future-proof’ electricity grid

Grid operator Fluvius has completed major renewal works on the electricity grid in Ronse. In recent months, it has built two brand-new switching stations, connected to a fully modernised transformer station. These are crucial nodes in the electricity grid, ensuring that residents of Ronse and the surrounding area can continue to rely on a stable and reliable energy supply in the future.

Phase 1 successfully completed

The key nodes in the electricity grid serving Ronse and the surrounding area were due for renewal and were close to their capacity limits at peak times. Ronse’s existing transformer station, one of the 250 most important electricity nodes in Flanders, therefore needed to be modernised and expanded to provide additional capacity and connection options.

Fluvius and transmission system operator Elia, the client for the transformer station, therefore launched a major renewal project. The transformer station was thoroughly refurbished and upgraded to meet all modern standards and incorporate the latest technologies, including remote monitoring and control.

At the same time, Fluvius built two new switching stations in Ronse: Schakelpost Gas and Schakelpost Vierwegen. These large new electricity substations are supplied by the transformer station and can each serve a wide area with electricity. Together with the installation of new electricity cables, they form the beating heart of the region’s new ‘future-proof’ electricity grid.

Work progressed smoothly, with no major disruption to local residents

Wim Verkest, electricity operations officer at Fluvius: “Both the construction of the new switching stations and the installation of the associated feeder cables were carried out according to a meticulously planned schedule. This meant that each stage of the work quickly followed the last, allowing the project to progress smoothly. Work on the new feeder cables began on 24 August, and phase 1 was completed on 19 November, entirely on schedule. We are pleased to have carried out these extensive works without causing major disruption to local residents. Only Kapellestraat had to be closed for a time, from Spinstersstraat to Molekensstraat. A diversion was provided via Molekensstraat and Bierinkstraat.”

Phase 2

Some of the load at the refurbished transformer station has meanwhile been transferred from the old feeder cables to the new ones. Phase 2 of the works will start in October 2022 and will involve no disruption or roadworks. Transmission system operator Elia will then move the large transformers within the station. Fluvius can subsequently transfer the remaining old supply cables to the new ones, but local residents and businesses will not notice any difference.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenewing pipelines and sewers
  • SubjectGeneral
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.