Fluvius combines utility works for R0 redevelopment with grid reinforcement in Machelen

Fluvius is stepping up work to reinforce the electricity grid in Machelen (Flemish Brabant). New electricity substations have been installed on both sides of the Brussels Ring Road near Petrus Schroonsstraat, and heavier cables are being laid in surrounding streets. This will prepare the grid for the growth in electric vehicles, solar panels and heat pumps over the coming decades.
The works are closely aligned with the redevelopment of the Brussels Ring Road (R0), which will require many cables and pipelines to be relocated in the coming years. To carry out this work as efficiently as possible and minimise disruption, Fluvius is working with De Werkvennootschap and other utility companies through the Synductis partnership.

Coordinating works as much as possible
De Werkvennootschap, known for major mobility projects such as the redevelopment of the Vilvoorde Viaduct, the reconstruction of the R4, Gentspoort and the North-South connection in Limburg, is working on the redevelopment of the Brussels Ring Road and the construction of a tram line to the airport.
The redevelopment of the R0 is divided into 33 work zones (25 on the ring road and 8 for the airport tram), spread over several years. Major changes are being made in these zones, including new cycle paths, bridges and road junctions. Fluvius needs to relocate cables and pipelines in 13 of these zones. Wherever possible, this work is being combined with investment under its own grid reinforcement plan, including upgrades to substations and the installation of a total of 25 kilometres of heavier electricity cables.

Electricity grid upgrade in Machelen
“Here in Machelen, De Werkvennootschap will increase the distance between the R0’s slip roads and interchanges,” says Johan Job, project manager at Fluvius. “The bridge over the R0 along Petrus Schroonsstraat, where our utility lines currently run, will also be completely rebuilt. To accommodate this, we have built new electricity substations on both sides of the ring road.”
“We have combined this work with essential reinforcement in the centre of Machelen, including the installation of new 400-volt low-voltage cables. This work is taking place in Petrus Schroonsstraat, Villastraat, Oudstrijdersstraat, Henri Brounstraat, Viaductstraat, Pierre Raedemaekersstraat and Georges Ferréstraat. In the coming years, we will apply the same approach at other locations along the ring road. In the longer term, De Werkvennootschap also plans to build two large service ducts beneath the ring road, where all utility lines can be grouped together, including our higher-capacity electricity cables.”