DCA Infra showcases its versatility and experience in Keerbergen
Text Niels RouvroisImage DCA Infra

Commissioned by the municipality of Keerbergen and working to a design by Tractebel, DCA Infra is currently carrying out a major redevelopment of the village centre. Removing the existing surfacing, earthworks, installing a separate sewer system, constructing new carriageways, installing a fountain and street furniture … both the underground and above-ground infrastructure are undergoing a major transformation. “Our aim is to complete the works in April 2024,” says Pascal Vekemans, project manager at DCA Infra.
Work in Keerbergen began in autumn 2022. The municipality’s goal in undertaking a major overhaul of the village centre is to make it greener, more pleasant and livelier. Alongside renewing the above-ground and underground infrastructure, the plans include planting 65 new trees to increase greenery. More than 1,900 m² will also be depaved to make way for an ‘experience square’. A large planted area with mature trees will screen the square from the car park and create a green oasis in the rest of the municipal square. Pascal Vekemans: “Following a design process that lasted around 10 years, DCA Infra started the demolition works in 2022 as main contractor. DCA Infra is also responsible for completing the entire street. Only the landscaping is being carried out by a specialist subcontractor.”

Permeable drainage system
The carriageway is being surfaced in exposed aggregate concrete, while the footpaths and parking bays are being laid partly in cobbles and partly in paving blocks. In total, around 1,900 m² will be depaved. “A completely new separate sewer system has been installed, with rainwater (RWA) disconnected from the wastewater sewer (DWA). Permeable pipes have been installed for the RWA, allowing as much surface water as possible to infiltrate into the ground.”
Working in a village centre is always a challenge, both in practical terms and in execution, even for an experienced contractor like DCA Infra. “There are many businesses in the work zone, so every day we focus on ensuring easy access to both the shops and the homes. DCA Infra has more than 50 years of experience in road construction, including installing new sewers and redeveloping streets. We are also no strangers to working in village and city centres. In the past, we have worked on the centres of Wijnegem, Itegem, Wiekevorst, Kasterlee, Beringen, Lier and Eilandje Antwerpen, among others.”

5 phases
The works are divided into 5 phases and are progressing smoothly. “We are currently in phase 4, where we have started rebuilding the street. Over the coming weeks, the programme includes the asphalt sandwich layer (intermediate layer), slipform paving to construct the kerbs in situ, and the concrete carriageway surfacing. The footpaths, parking bays and planting areas will follow. If everything goes to plan, the entire project, including all phases, should be completed by next summer. Our aim is to complete the works in April 2024,” concludes Pascal Vekemans. ■

The DCA Infra DNA
DCA Infra presents itself as a reliable partner, offering a tailored solution to every requirement, from major public collector sewer projects to the construction of private car parks. Supported by an in-house design department, experienced and committed employees take a considered approach to every project. Collaboration is key. Good collaboration leads to the best results. “That is why we always agree clear arrangements and welcome ideas from our partners and employees,” the company says.
DCA Infra works in both the public and private sectors, from sewer construction to site development and civil engineering. “This means we can deliver a comprehensive package, always showing respect for our partners and employees. We also place great importance on a safe working environment and personal development. We have a hands-on Kempen mentality: we roll up our sleeves, work hard and keep our feet on the ground. Respect for the communities where we work is essential too. That is why we communicate clearly and accurately with residents.