Sinking of fourth tunnel section temporarily halted after sand build-up

The sinking of the fourth section of the Scheldt Tunnel has been temporarily halted. Unexpected sand build-up occurred in the immersion trench while the 60,000-tonne element was being positioned. As a result, the tunnel section is not fully in its planned position. “Despite thorough preparations and extensive simulations, this kind of sand build-up remains an unpredictable natural phenomenon in a highly dynamic river such as the Scheldt. Sinking a tunnel section is a partnership between precision engineering and nature,” said Laure Stuyck, spokesperson for client Lantis.
Following an analysis, it was decided to leave the tunnel section resting on the riverbed for at least two weeks. This is necessary because the slack-tide window, when the current in the Scheldt is at its weakest, is passing. As a result, corrective work is not currently possible. The tunnel section will be monitored continuously, and the immersion catamarans will remain on site to maintain control. In the meantime, the contractor consortium TM COTU* and client Lantis are investigating whether the element needs to be raised again or whether its position can be corrected in another way.
The delay to the process of sinking the tunnel sections, which is partly due to the limited availability of suitable slack-tide windows, is estimated at around one month. However, this delay will not affect the planned opening of the tunnel: this remains scheduled for 2028 for cyclists and 2030 for motorised traffic.
As announced yesterday, the current closure will be lifted on 22 August at 6 am to minimise disruption to through traffic. The shipping channel will, however, remain closer to the right bank for a further six weeks. Crossing traffic will not be permitted, and speed restrictions will apply. Any additional closures, for example if the tunnel section has to be raised, will be planned and communicated in good time, with due consideration for the impact on shipping.
*TM COTU stands for Tijdelijke Maatschap Combinatie Oosterweeltunnel. The group comprises the Belgian construction companies BESIX, Stadsbader Contractors, DEME and Jan De Nul.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeExtending the life of bridges and tunnels
- SubjectBridges & tunnels