Sustainable reinforcement of Arnhem’s Rijnkade with special retaining walls
Text and images Bosch Beton

To ensure that the Rijnkade in Arnhem meets future climate and high-water scenarios, Bouwcombinatie SAMEN (G. van der Ven aannemingsbedrijf, Ballast Nedam & Hakkers) is working on the flood defence reinforcement on behalf of Waterschap Rijn en IJssel and the municipality of Arnhem. This project in Arnhem is unique in the scale of its almost entirely zero-emission construction work. This focus on sustainable construction prompted the choice of Bosch Beton’s precast retaining elements.
A sustainable tender
The tender for this large-scale project deliberately prioritised emissions reduction through specific requirements and award criteria. The contract included requirements for sustainable, zero-emission construction and minimal noise nuisance for the surrounding area. The points awarded for each individual requirement counted as a notional discount on the contract sum. This enabled contractors to submit market-based tenders while being encouraged and rewarded for innovative sustainable solutions.

The role of MEAT criteria in sustainable choices
As the MEAT criteria focused on emissions reduction, Bouwcombinatie SAMEN took the initiative to use precast retaining walls for the flood defence. These walls are more environmentally friendly than in-situ concrete because they generate no additional emissions on site. The walls were also transported to Arnhem by a zero-emission lorry, further reducing emissions. Transporting some of the walls by water caused much less disruption along the quay, earning the consortium points for its construction plan as well.
A challenging project
Special retaining walls and suspended aprons had to be designed for this project. Because it could produce a large number of bespoke elements within a short timeframe, the consortium decided to appoint Bosch Beton as the retaining wall supplier. The dimensional accuracy of these precast walls gave Bosch Beton an advantage both in reducing emissions and in minimising disruption to the surrounding area.
A future-proof Rijnkade
The flood defence is being completely renovated along a 1.2-kilometre stretch. Work began in autumn 2023, and the new Rijnkade is expected to be completed this year. Thanks to the innovative and sustainable approach, the Rijnkade will remain safe in the future.
A business enquiry for Bosch Beton? Get in touch
Wie aan Rijnkade werkte
- prefab keerelementen
Bosch BetonMentioned in Sustainable reinforcement of Arnhem’s Rijnkade using special retaining walls
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRijnkade
- SubjectHydraulic engineering
- CompanyBosch Beton