Hydraulic engineering

New quay walls protect Blankenberge

Uitvoering van de bekisting en de wapening van de kopbalk met zicht op de doorvoeren van de legankers en afvoer van de riolering.
Uitvoering van de bekisting en de wapening van de kopbalk met zicht op de doorvoeren van de legankers en afvoer van de riolering.

In September 2020, the Agency for Maritime and Coastal Services and the Local Authority of Blankenberge began the final stage of projects around the marina to protect the town and its hinterland from severe storm surges. At the same time, Herbosch-Kiere is building new quay walls in Havenstraat and Franchommelaan.

The storm wall around the marina prevents flooding via the harbour. The Barcadère, the area between Havenstraat and Vismijntje, and the openings in the wall that provide access to the promenade are now the last weak links in the defences. Alongside the works to protect the town from severe storm surges, new quay walls are also being built in Havenstraat and Franchommelaan. The existing sloping revetments are outdated and prevent the marina from being deepened. They would fail during dredging. Finally, Franchommelaan will be straightened. 

The first section of quay wall to be tackled is at the Barcadère. Ing. Geert Stellamans, project director at Herbosch-Kiere, explains: “To enable work to be carried out in the old marina, a temporary wall was first driven into the ground so that all the subsequent works could be carried out in ‘semi-dry’ conditions. A wall of sheet piles was therefore driven a few metres in front of the location of the new quay wall, towards the water.” 

Steel sheet-pile wall

Herbosch-Kiere is now building the new quay walls. Geert Stellamans: “The new wall consists of a steel front wall made from AZ44-700N sheet piles and, in a very limited area, CAZ44-700N tubular piles, forming a combi-wall to create the new front wall. The combi-wall is used locally because the subsoil in that area is weaker. There is a layer of Gyttja there, an organic sediment consisting of decayed peat.”

Driving the new front wall in Havenstraat is under way.

Capping beam

A concrete capping beam will be installed on the steel front wall, rising to the level of the road surface, approximately +6.55 m TAW. For reasons of overall stability, the concrete front beam is connected to a second row of sheet piles. This is the anchor wall, which was driven further inland. A connection between the front wall and the anchor wall is needed to achieve overall stability. The two walls are connected using tie rods. The tie rods are fed through sleeves in the front wall and anchor wall. An anchor plate will be installed in a recess, and the ground anchors will be secured with a nut after being prestressed. 

Geert Stellamans: “A P2 system has been provided to protect the anchors against corrosion. The first level of protection (P1) is the galvanising of all the anchors. For the second level of protection (P2), the anchors are fully enclosed in a PE pipe. After the anchor has been tensioned, the remaining space between the anchor and the PE pipe will be filled with cement grout. In several areas, additional anchoring with ground anchors is required because the cofferdam structure is narrow, meaning the distance between the front wall and the anchor wall is limited. The anchor wall in Havenstraat and part of the one in Franchommelaan will therefore also be secured with injection anchors.”

Further backfilling

Once the new front wall and the necessary anchors have been built, further backfilling is planned so that the new superstructure can be constructed. Geert Stellamans: “To provide protection against storm water levels, storm walls will be built to fully screen off this part of the marina from the surrounding areas. The storm walls will be made of reinforced concrete, with architectural concrete coping stones along the top. They will connect to the walls built in the previous phase. Two stepped structures will provide pedestrian access between the areas in front of and behind the storm walls. Two roller shutters and a mobile flood barrier will provide access to the parking area. They can be closed in the event of a flood risk.”

Alongside the construction of an urban square with pavements, new roads and parking, wooden planters with marram grass, seating blocks and benches will enhance the location, making the site a usable part of the harbour once again. If everything continues according to plan, this attractive part of Blankenberge will be fully accessible and protected again by the start of 2022.     

Een zakelijke vraag aan Herbosch-Kiere? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectHydraulic engineering