Damaged Berendrechtsluis wall successfully repaired

Berendrechtsluis in Antwerp is ready for use again. In December last year, a lock wall was seriously damaged by one of the many vessels passing through the lock. Herbosch-Kiere was brought in to replace the wall and did an excellent job. “The aim was to get the lock operational again as quickly as possible, and we succeeded,” says Ernest Baele, site manager at Herbosch-Kiere.
At the end of last year, Berendrechtsluis in the Port of Antwerp was damaged when a vessel struck the lock wall while leaving the lock. This caused serious cracks in the wall, allowing water to flow into the lock chamber. Port of Antwerp called on Herbosch-Kiere’s expertise to restore the lock. Jannes Meeusen, site manager at Herbosch-Kiere: “It was important to be able to work in dry conditions, but that is obviously not ideal at a lock. On the waterside, we installed a cofferdam 20 m long and 5 m high. It was mounted against the quay wall, giving us a dry work area on the waterside too.”

Concreting the lock wall in the first phase.
34 tonnes
To remove the damaged lock wall, it was sawn into sections. “We called on Stenabo, specialists in concrete drilling and sawing,” says Ernest Baele, site manager at Herbosch-Kiere. “We have worked successfully with them several times in the past, but never on a hydraulic engineering project. The collaboration went very smoothly this time too. The wall was sawn into several sections, and the pieces, the heaviest weighing up to 34 tonnes, were lifted by a 280-tonne crane, placed on a pontoon and taken away by water.”

Installing prefabricated reinforcement cages with HSC70t on Dongestroom.
The next step was to build a new lock wall. Jannes Meeusen: “The damaged section had to be removed completely. Renovation was not an option, as the wall had suffered structural damage. There is also a fixed bridge resting on the wall. The damaged wall could no longer withstand either the pressure of the bridge or the pressure of the water in the dock. In short, the wall was shuttered, reinforced and concreted again. It is 13 m long, between 1.2 m and 1.9 m thick, and over 7 m high. This was certainly not an everyday job for Herbosch-Kiere, but we have the experience and expertise needed to bring complex projects like this to a successful conclusion.”

The new lock wall.
Time pressure
The speed at which the work had to be carried out was an additional challenge for Herbosch-Kiere. Ernest Baele: “There was some time pressure. For the client, Port of Antwerp, it was important to get the lock operational again as quickly as possible. So, throughout May, work continued on public holidays and at weekends. Combined with the technical complexity of the work, this made the project particularly interesting.”
Berendrechtsluis is now fully operational again. “As well as replacing and finishing the lock wall, we also fitted it with new fender beams. The bridge was back in operation at the beginning of August. It was locked in a vertical position while work was being carried out on the lock wall. ENGIE Fabricom, Bosch Rexroth and Kalmar worked as subcontractors for Herbosch-Kiere on the bridge works. We are very pleased with the outcome, especially as it was quite a feat. Port of Antwerp is also happy with the result. We stuck to the schedule and delivered high-quality work. The new wall looks very good, with neat, straight concrete,” concludes Jannes Meeusen.
Een zakelijke vraag aan Herbosch-Kiere? Get in touch
Wie aan Berendrechtsluis werkte
- clientHavenbedrijf AntwerpenMentioned in Drilling and sawing specialist cuts lock wall into 12 sections
- werken aan de brugENGIE FabricomIn this story
- werken aan de brugBosch RexrothIn this story
- werken aan de brugKalmarIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBerendrechtsluis
- ThemeStrengthening waterways and coastlines
- SubjectHydraulic engineering
- CompanyENGIE Fabricom
- CompanyBosch Rexroth
- CompanyKalmar
- CompanyHerbosch-Kiere