Hydraulic engineering

Antwerp | Quay wall renovation

Antwerp | Quay wall renovation

Adapted dewatering technique for quay wall renovation in Antwerp

Existing quay walls on the right bank of the Scheldt are being renovated in Antwerp. The Scheldekaaien joint venture has been using the services of G. Smeyers for the dewatering works since the tender stage. G. Smeyers prepared the dewatering study using a 3D computer simulation and is currently working on site, where the excavation for the anchor wall is being dewatered using vertical wellpoints and piston pumps at two levels. 

On 25 November 2013, Waterwegen en Zeekanaal nv put out a tender for the renovation of the existing quay wall on the right bank of the Scheldt. The works are located along d’Herbouvillekaai and Ledeganckkaai in Antwerp. The Scheldekaaien joint venture, a temporary association of the companies Artes Roegiers, Herbosch-Kiere and Hye, stated at the tender stage that it intended to use the services of G. Smeyers of Zandhoven for the dewatering works. The tender documents had to include a detailed dewatering study based on a 3D computer simulation.  

“As we have our own specialist design team, preparing such a study was no problem for us,” says G. Smeyers. The combination of the Scheldekaaien joint venture and G. Smeyers nv was successful in the tender, and after a brief review of the bid, the first part of the contract was awarded to the Scheldekaaien joint venture.  

Renovatie kaaimuren

The 19th-century quay walls are in need of renovation.


Renovation of 19th-century quay walls
The existing quay walls were built towards the end of the 19th century in two sections. The northern section, approximately 3.5 kilometres long, was built between 1878 and 1886. The southern section, also known as the Zuiderkaaien, approximately 2 kilometres long, was built between 1897 and 1903. The quay walls to be stabilised in the work zone are located exactly where the northern and southern sections meet. 

The quay walls in both sections were built using the same technique. Their foundations consisted of individual steel caissons sunk pneumatically. The working chambers at the bottom of the caissons were filled with concrete after sinking. A separate wall was then built on each foundation caisson, up to the low-water level, under the protection of a cofferdam. The joints between the individual sections below the low-water level were filled with concrete. Above the low-water level, the masonry was built continuously across adjacent sections. 

The quay walls soon proved to be insufficiently stable. Subsidence and movement of the walls were observed from the time they were completed. 

The quay wall renovation was divided into five sections of approximately 100 metres each. Phases 3 and 4 are now under way. First, a combi wall is installed in the Scheldt in front of the existing quay wall. The excavation pit is then enclosed by driving sheet piles at both ends and along its landward side. Both the combi wall and the sheet piles are driven deep into the Boom clay, forming a watertight cofferdam. Inside the cofferdam, part of the existing quay wall is demolished ‘under water’, and the pit is pumped dry using open dewatering. 

Dewatering using vacuum deep wells
The rear quay wall serves as an anchor wall. It must be excavated on its landward side to a depth of 10 metres below ground level. A dense array of tie-back anchors must be installed between the combi wall and the anchor wall, then tensioned from the landward side of the anchor wall. To carry out this excavation ‘in the dry’, substantial dewatering had to be installed on the landward side of the anchor wall. The groundwater level had to be lowered from +4.00 TAW to -3.00 TAW. 

Given the depth to which the groundwater level had to be lowered, vacuum deep wells were chosen for the dewatering works. The results were not ideal: due to the presence of low-permeability layers, a significant amount of residual water continued to flow into the excavation. 

Renovatie kaaimuren

G. Smeyers prepared a detailed dewatering study using a 3D computer simulation.

Change to the installation method
From phase 2 onwards, G. Smeyers, in consultation with the Scheldekaaien joint venture, opted to change the dewatering method, switching from vacuum deep wells with submersible pumps to a staged system using vertical wellpoints and piston pumps at two levels: a first row of filters at +4.00 TAW and a second row at +1.00 TAW.

In this second phase, the filters are installed at close intervals of 2.5 metres, and the boreholes are completely backfilled with drainage sand. This method has proved highly effective. The excavation pit can now be excavated without residual water flowing into it through the low-permeability layers.  

The change to the installation method means the contractor’s work can be carried out in much more comfortable conditions. “The change to the dewatering method we proposed was highly effective, and we implemented it without any impact on the budget, something our client greatly appreciated,” says G. Smeyers. “Clients who put their trust in our company from the tender stage onwards can continue to rely on us throughout the works, whatever problems arise.”

A business enquiry for Smeyers nv? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectHydraulic engineering
  • CompanySmeyers nv
  • CompanyHerbosch-Kiere