Noorderlijn, Antwerp | “Within the wider Noorderlijn project, this handover is the biggest milestone to date”

At the weekend of 7 and 8 December 2019, the two new tram lines in Antwerp, which will improve the city’s accessibility, officially entered service. At the same time, the Opera pre-metro station also opened its doors. It was a substantial project, with BAM Contractors carrying out the civil engineering, infrastructure and roadworks. “Within the wider Noorderlijn project, this handover is the biggest milestone to date,” says Nicolas Cooreman, senior project manager at BAM Contractors.
Antwerp tram line inaugurated after logistical and technical feat
Noorderlijn is a project by Vlaamse Vervoersmaatschappij De Lijn, the City of Antwerp and the Flemish Agency for Roads and Traffic. It aims to improve road safety for all road users and ensure the city remains liveable. BAM Contractors, the THV BAM Infra Rail, BAM Track and ENGIE (together, Tramcontractors Bouw) worked on this major mobility and urban development project for more than four years. Their contribution has helped achieve two goals at once: improving traffic flow and supporting the transition to sustainable mobility solutions. The scale of the project is illustrated by just a few figures: 86,000 m³ of concrete, 80,000 tonnes of asphalt, 115,000 m² of natural stone, 330,000 m³ of earthworks, 22 km of sewer pipes, 47,000 m² of landscaping and 30,000 sleepers.
The major works began in 2016 and included not only the construction of new tram lines and roads, but also road safety improvements to the Noorderleien and other major traffic routes. The new tram runs along the Noorderleien, past Spoor Noord and Kempenstraat, to its terminus at Havana in Luchtbal. New tram connections also link Eilandje and Havenhuis to the city centre. “BAM Contractors was responsible for all the civil engineering, infrastructure and roadworks, including the finishing works. The THV BAM Infra Rail and BAM Track, in turn, carried out the track works,” says Nicolas Cooreman.

The THV BAM Infra Rail and BAM Track carried out the track works. (Image: François De Ribaucourt)
A broad scope of work for BAM
BAM was responsible for the structural and finishing works for the renovation of the Opera pre-metro station, an underground car park for 340 cars and two new 550 m-long road tunnels beneath Opera Square. Nicolas Cooreman says: “We also built a new pre-metro tunnel, a park-and-ride car park and cycle parking facility at the Havanasite, a new steel tram bridge and a new Londen-
brug. Opera Square was made more pedestrian-friendly, and BAM also created the archaeological garden at Kipdorpsite and renovated the Hardenvoortviaduct.”
BAM also built a tram-bus lane and reconstructed the road and sewer infrastructure on Noorderlaan, between Groenendaallaan and Ekersesteenweg. The roads and sewers were reconstructed on Frankrijklei, Italiëlei, Rijnkaai, Tavernierkaai, Bataviastraat, Dinantstraat and Sint-Laureiskaai, while the road, sewer and bus infrastructure at F. Rooseveltplaats was renewed. The tram line was also extended over a 7 km route, including the construction of the associated tram tracks (18 km) on the Leien, Noorderlaan and Eilandje.

The major works began in 2016 and included not only the construction of new tram lines and roads, but also road safety improvements to the Noorderleien and other major traffic routes. (Image: François De Ribaucourt)
A logistical challenge
BAM was also responsible for coordinating and carrying out the necessary utility diversions and managing disruption during the works. Nicolas Cooreman says: “The biggest challenge was undoubtedly the logistics, both above and below ground. Working in the middle of a city is never easy. On the one hand, you need space for work and storage; on the other, there is a great deal of stakeholder management involved. Local residents, shopkeepers, tourists, vulnerable road users and drivers all want disruption to be kept to a minimum, while the tram itself has to keep running. There are many stakeholders to take into account. The Leien themselves were closed to traffic, but the intersecting tram lines remained in service.”
BAM also faced a number of challenges underground. The structural works for the underground car park, cycle parking facility, metro station and road tunnels beneath Opera Square took place at the same time as the above-ground structural works. “Because the structural works were carried out simultaneously, the roof slab was installed first over the
underground infrastructure. Work then proceeded downwards. This also meant that loads could be applied above ground. It was not a standard solution, but it allowed work to take place above and below ground at the same time. This was a project that gave BAM the opportunity to make full use of all its strengths. We have extensive experience in engineering, delivery and logistics. Within the even wider Noorderlijn project, this handover is the biggest milestone to date,” concludes Nicolas Cooreman.