Sewerage & underground infrastructure

Finishing works on Mechelen tangent in full swing

Finishing works on Mechelen tangent in full swing

Autumn 2019 marked the start of a new phase in the Mechelen station project. In October, Willemen Infra and Franki Construct, both part of Willemen Groep, began work on the finishing of the tangent as a temporary joint venture, a project expected to take around 2.5 years. While Franki Construct is focusing on the structural works and finishing, Willemen Infra is responsible for all the (temporary) roadworks and drainage works. “As sister companies, we work extremely well together, which is a major asset on projects as complex as this one”, they say.

Work on the station project in Mechelen began in 2013. A cooperation agreement was signed between NMBS, Infrabel, De Lijn, the city of Mechelen and the Flemish government. The project, spread over several years, includes a new double track on the existing Brussels-Antwerp railway line, a new access road between Brusselsesteenweg and Douaneplein, and a road tunnel between Leuvensesteenweg and the station. The existing train and bus station is also being completely rebuilt, with excellent facilities and connections for cyclists and pedestrians.

The structural works on the tangent were completed a year and a half ago by a consortium that included Franki Construct. “At the time, we were in a temporary joint venture with Jan De Nul, Besix and Bam Contractors, working for TUC RAIL”, says ir. Stijn Seghers, head of civil engineering at Franki Construct. “That package included the structural works from Brusselsesteenweg to Douaneplein, among other things. The station car park at the rear of the station was also redeveloped at the same time, but that work was not part of our scope.”

The project is expected to take around 2.5 years.

Finishing the tangent

The structural works were completed in 2017. The tunnels beneath the railway at Brusselsesteenweg and a new bridge over the Dijle, among other structures, are already in place. Tendering for the finishing works on the tangent began that same year. The works include the construction of new junctions, the road surface, new cycle paths and footways, as well as several cycle tunnels and bridges.   

Willemen Infra and Franki Construct are carrying out the work as a temporary joint venture (TM). Following some preparatory works, which began in May 2019, the TM started the actual finishing works on the tangent in October.

First, Brusselsesteenweg is being connected to the new tangent. At the same time, a new cycle bridge is being built over Brusselsesteenweg, linking it to Kruisbaan. Jubellaan is getting a new junction connecting to the new road tunnel beneath the Leuven Canal. The junction of Europalaan and Jubellaan is being converted into a T-junction, and a cycle tunnel beneath Jubellaan will open onto Colomalaan and the Colomabrug.

“The great strength of this TM is that we have all the necessary expertise in-house for a site like this.”

Cycle route puzzle

The tangent and its footways and cycle paths continue across Leuvensesteenweg. A new cycle connection is also being built there, known as the cycle route puzzle. The route of the future tangent is already clearly visible between the railway and De Loods event venue. A new junction is also being built here to connect the N15 to the new access road. The tangent is 2.6 km long in total. It is intended to ease congestion both around the station and on the ring road around Mechelen (R12), and improve through traffic flow. If all goes to plan, the connecting road will open to traffic at the end of 2021.

“In short, the tangent takes Brusselsesteenweg, one of Mechelen’s main arterial roads, all the way around the city centre”, explains Kristof Aernouts, project director at Willemen Infra. “Part of the route of Brusselsesteenweg is being moved out of the city centre and rebuilt, with a strong focus on safe cycling and walking connections in the form of three cycle tunnels and two cycle bridges. We have now been working for a good year, including the preparatory works, and progress is good. Willemen Infra is responsible for the drainage and roadworks.”

img_3141-kopieren

“In short, the tangent takes Brusselsesteenweg, one of Mechelen’s main arterial roads, all the way around the city centre.”

Working across the site

At the end of August, Franki Construct will start finishing the first tunnel bore. Ir. Stijn Seghers: “This includes everything from fire-resistant spray coatings and cladding to the general tunnel fit-out. The tender also includes a major package of systems for fire protection, ventilation and lighting, covering the entire tangent, including the car park behind the station. The car park itself is complete, but we are managing traffic flow. At the moment, we are working in various zones along the whole route, on everything from earthworks and concreting to finishing.”

Willemen Infra is also working at full pace. Temporary roads have already been built to allow excavation pits to be dug, and the drainage works are also well advanced. As work has to be carried out alongside existing traffic throughout the site, no roads can be closed completely, so the work has to be phased. It is no surprise that a complex construction project spanning almost three kilometres takes a great deal of time. The logistics involved are considerable. Kristof Aernouts: “The ‘minimise disruption’ principle plays an important role throughout, and the authorities have made that very clear. The TM has therefore drawn up a separate programme for this, with a strong focus on keeping car, cycle and pedestrian traffic safe and minimising disruption for local residents during the works. The associated mitigation measures amount to around 1.5 million euros.”

Working well together

Alongside the logistics, Willemen Infra and Franki Construct see the schedule as the biggest challenge. “That is typical of a major construction project like this”, says ir. Stijn
Seghers. “And then the coronavirus situation came along as well. As far as the structural works are concerned, we have everything under control and can make up the lost time without any problems. The supply of materials, on the other hand, caused more difficulties. The fire-resistant spray material, for example, had to come from France. Given its short shelf life, this product is made almost to order, so there is virtually no stock. That caused a few problems, but nothing insurmountable. On projects like this, where planning is crucial, our strong relationship with sister company Willemen Infra is a real advantage. We work extremely well together and know each other inside out. We can respond quickly as a team and keep optimising the schedule.”

Kristof Aernouts agrees: “Willemen Infra and Franki Construct are certainly no strangers to one another. We have worked together many times before and always pull in the same direction. That experience means we complement each other very well. For both parties, this is a technically bespoke project, and it is a major advantage to be so well aligned on planning too. The great strength of this TM is that we have all the necessary expertise in-house for a site like this. There is no problem on site that we could not solve ourselves.”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectSewerage & underground infrastructure
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.