Sewerage & underground infrastructure
Designed intelligently with BIM, built sustainably
Text and images Deschacht

Designed intelligently with BIM, built sustainably! That sums up the large-scale BIM engineering project for JV GOSSELIN-WDP NV in Bilzen. Building a huge distribution centre there called for more than a standard water management solution. The entire project was developed in a BIM environment by Deschacht.
This large-scale industrial construction project covers approximately 50,000 m² of buildings and 52,000 m² of paved areas. Designing an efficient water management system for this area was no easy task, particularly given the heavily trafficked transport zones. Architeam developed the concept plans to meet the strict permit conditions. The design combined swales across the site’s green areas with infiltration pipes beneath the many heavily trafficked paved areas. Working with Deschacht, the concept was optimised and fully modelled in 3D so that every detail could be worked out. “The BIM design proved a major asset here. Visualising everything in 3D meant potential clashes could be identified during the design phase, giving us a clearer picture of complex underground conditions from the outset,” says Olivier Christiaens, estimator at Matthysen BV.
Swales to provide the required storage volume
One of the design challenges was meeting the permit conditions for storage volume and infiltration area. To achieve this, we positioned swales at different levels across the site. This solution ensures the correct ratio of connected area to storage volume. It also meets statutory requirements, while the swale system can efficiently handle peak flows during heavy rainfall.

Storage solution for heavily trafficked areas
The heavy point loads from stackers (heavy industrial forklifts) added to the complexity. Following a targeted risk analysis, we moved the storage system from beneath the heavily trafficked areas to a ring collector system using IT-PP Ribwall infiltration pipes (SN8) around the site. These pipes ensure controlled, even distribution of rainwater across the site. Their high stiffness and structural, mechanical and hydraulic properties make them ideal for a complex environment such as this. The IT-PP Ribwall pipes were also used to manage drainage from the loading bay, where installation depth was limited and loads were high. This was a technical feat, with minimal cover and load-bearing capacity both critical.
BIM as a driver of precision and efficiency
The entire project was developed in a BIM environment by Deschacht, which was crucial for accurately calculating volumes and areas. The 3D model enabled every level, from the sewer system to ducting for future infrastructure such as EV charging points, to be fully planned in advance. “We delivered this project using the detailed 3D plans on site,” says Wesley Verschueren, project manager at Matthysen BV, who oversaw the earthworks. “This allows us to work much faster and more efficiently, as we no longer have to contend with potential structural issues when installing the pipes. The 3D view takes the pressure off us during the preparation process, making installation on site run more smoothly.” Olivier Christiaens adds: “BIM manager Filip Roels could retrieve all the required information directly from the BIM system. For example, he could easily track changes in material use with each revision, which was a major asset when preparing progress statements for a project with many changes.”
“We never shy away from a challenge,” says Olivier Christiaens. “At Matthysen BV, our motto is: ‘Nothing is impossible.’ This site was a real race against time. We started with revision 0 (6.3 km of sewer pipes) and have since reached revision F, with a total of 11.2 km of sewer pipes. The quick response from Deschacht’s Hasselt branch, led by Frank Decosemaeker, was also crucial to completing every phase on time.”

Digital modelling, a sustainable construction choice
This project shows how technical expertise, strategic material selection and digital planning come together in a sustainable, future-proof solution. Combining smart hydraulics with digital modelling has resulted in an efficiently managed site, ready to meet the challenges of today and tomorrow.
Een zakelijke vraag aan Deschacht? Get in touch
Who worked on it
Distributiecentrum JV GOSSELIN-WDP NV Bilzen in Bilzen-Hoeselt
- BIM-engineering
Deschacht - conceptplannenArchiteam
- groundworksMatthysen BV
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDistributiecentrum JV GOSSELIN-WDP NV Bilzen
- SubjectSewerage & underground infrastructure
- CompanyDeschacht
- CompanyArchiteam
- CompanyMatthysen BV