Transformation of Schumanplein gets under way

PROJECT: REDEVELOPMENT OF SCHUMANPLEIN
It’s official: work on Schumanplein has begun. Today, the politicians involved marked the start of the transformation of this busy roundabout in the heart of the European Quarter into a proper square centred on meeting people and active mobility with a ceremonial first spade in the ground. The works will take more than 2 years. Brussels Mobility, which has overseen the project to date, is now handing over responsibility for the works to Beliris, the federal client for construction projects in Brussels.
The works will extend beyond the square itself to include Wetstraat from the bridge on Etterbeeksesteenweg, Kleine Wetstraat and Blijde Inkomstlaan. The design by Danish architects COBE and Brussels-based BRUT brings the greenery of Jubelpark through to the square via a pedestrian promenade along Kleine Wetstraat.
The works are being carried out by contractor Colas Noord. The total cost is €25,000,000 excluding VAT, of which €17,400,000 excluding VAT is funded by the European Recovery Plan, with the remainder covered by Beliris.
The works will be carried out in several phases. The first phase, from 20 November to 22 December 2023, will involve demolishing the centre of the roundabout. During this phase, traffic will be restricted to two lanes on Kortenberglaan and the northern half of the roundabout (on the Archimedes and Kortenberg sides), and to one lane on the southern half (on the Froissart and Oudergemlaan sides). No diversions are currently planned, and public transport will continue to operate.
From 8 January until summer 2024, Blijde Inkomstlaan will be redeveloped to allow two-way traffic. Works will then continue on Wetstraat, concluding with the final landscaping of the square and construction of the canopy. The works are expected to take more than two years in total.

SHARED SPACE
The project’s overall design philosophy highlights Schumanplein’s central location, with concentric circles around the centre of the square, which will be covered by a canopy with a mirrored underside and a green roof. The square will be level throughout, allowing it to host events too.
A broad pedestrian promenade with benches, shrubs and trees will run around the square. As the tunnel beneath it leaves too little room for trees to be planted directly in the ground on the roundabout and in Kleine Wetstraat, large planters will be used in these areas.
Active mobility is being prioritised, with safer and more visible cycle lanes around the roundabout and on both sides of Wetstraat. The traffic circulation plan has been amended to make room for a zone for active transport. Motor traffic will be maintained between Kortenberglaan and Wetstraat and Archimedesstraat. The rest of the roundabout will be accessible only to buses, and no longer to cars.

THE HEART OF EUROPE
The new Schumanplein is intended to become a meeting place for the diverse groups of people who visit this hub of Brussels life. The project is part of a broader vision to make the European Quarter a pleasant place to live, where Europe comes to life on a human scale and all residents of Brussels, commuters and visitors are welcome.
QUOTES
KARINE LALIEUX, MINISTER RESPONSIBLE FOR BELIRIS
“Work is starting soon after the permit was issued. Beliris will be responsible for transforming the European Quarter in the heart of our capital. I am pleased that we can renovate Schumanplein and its surroundings and turn them into a dynamic, contemporary space that is more accessible to pedestrians, cyclists and people with reduced mobility. Beliris and its partners will do everything they can to ensure that the Schumanplein project, an important multimodal junction in the capital, is delivered in the best possible conditions. Implementing a phasing plan and providing comprehensive information will be important elements in supporting this exceptional project. The total cost of this major project is 25,000,000 euros. Alongside the substantial investment of €17,400,000 from the European Recovery Plan, Beliris is contributing €7,600,000 from its own funds.”
RUDI VERVOORT, MINISTER-PRESIDENT OF THE BRUSSELS-CAPITAL REGION, RESPONSIBLE FOR TERRITORIAL DEVELOPMENT
“This is another step towards transforming the neighbourhood into a more pleasant environment for institutions and businesses, as well as for residents today and in the future. This emblematic junction is a cornerstone of the shared vision for the European Quarter: a mixed, lively neighbourhood that is a more pleasant place to live because it can be shared more easily by everyone. It is an excellent example of our regional policy for a more accessible and better-integrated city.”
ELKE VAN DEN BRANDT, BRUSSELS MINISTER FOR MOBILITY AND PUBLIC WORKS
“People have been looking forward to this from Lisbon to Budapest, and in Etterbeek’s little streets too: work on the iconic Schumanplein starts today! Soon we’ll have a much greener, more liveable square that is safer for pedestrians and cyclists and easily accessible to people with reduced mobility. These improvements will allow the square to fulfil its role in the capital of Europe while also providing a peaceful, pleasant place for local residents.”
ANS PERSOONS, BRUSSELS STATE SECRETARY FOR URBAN PLANNING AND INTERNATIONAL AND EUROPEAN RELATIONS
“The new Schumanplein, planted with trees, free of cars and equipped with cycle lanes, is a symbol of our ambition for the European Quarter. We are transforming it into a neighbourhood on a human scale. The quality of public space plays an important role in that. The square will become the true link between Jubelpark, the Jourdan neighbourhood, the Leopold neighbourhood and the Squares neighbourhood. Situated between the various European institutions, this square is destined to become a new meeting place. A place where people don’t just want to walk through, but where they really want to spend time.”
PHILIPPE CLOSE, MAYOR OF THE CITY OF BRUSSELS
“This symbolic first spade in the ground marks a very important step for the capital of Europe. With all the European institutions around it, Schumanplein is the heart of Europe. The roundabout and its surroundings are now being transformed into a true meeting place. The redevelopment will also better connect residents with spaces that were not always easy to access.”
Question about this story? Ask your question
Wie aan Schumanplein werkte
- architectCOBEIn this story
- architectBRUTIn this story
- contractorColas NoordIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectSchumanplein
- SubjectPublic space
- CompanyCOBE
- CompanyBRUT
- CompanyColas Noord