Elegant steel ellipse overlooking the valley
Text Philippe Selke Beeld TMI

At the spectacular viewpoint at Le Jambon in Vresse-sur-Semois, an elegant elliptical structure in steel and concrete, weighing around 80 tonnes, rises above the valley. It offers visitors, including those with reduced mobility, breathtaking panoramic views. Building this architectural showpiece was a technical challenge that the TMI steelwork teams were delighted to take on. This exceptional project stands out from the more conventional structures they build every day, both functionally and aesthetically, showcasing their expertise all the more.
Complex geometry, refined aesthetics, very thin steel plates, a difficult-to-access site, a substantial cantilever … Although the project was by no means exceptional in scale for TMI, it was far from straightforward. Grégory Cimino, Project Manager at TMI, explains what made it so challenging.

Fabrication with complex geometry
The footbridge is elliptical in shape and slopes towards the valley, thanks to the variable depth of its box girder, which gives it variable stiffness. This curved and sloping form made fabrication particularly delicate. The structure weighs 80 tonnes in total, split equally between 40 tonnes of weathering steel and 40 tonnes of concrete. Before installation, the weathering steel was sandblasted to ensure even oxidation and a stable colour after a few months. The steel plates are just 10 to 20 mm thick, requiring great precision to prevent distortion. The footbridge comprises six sections, which were welded in their final positions at TMI’s workshops in Seilles (Andenne) to check quality and precision. This trial assembly made it possible to check the geometry and prevent assembly errors on site. “As welding heat causes distortion, the number of welders working simultaneously was limited to one or two to keep this distortion in check,” explains Grégory Cimino. “The specific sequencing meant that fabrication took about a month.”

Cantilever extending more than 10 metres
The structure comprises six sections, each weighing 6 to 7 tonnes, which made transport to the site easier. Installation at the Le Jambon viewpoint took place between June and August 2025, 50 metres from the road, among remarkable trees that had to be preserved. Grégory Cimino: “Temporary stainless steel structures were installed to allow the sections to be slid into place during assembly. Using a release system, the footbridge was slid several metres over its six concrete supports. This left half of the footbridge cantilevered in a single day. The earth-filled concrete trough acts as a counterweight, preventing the steel structure from tipping over and plunging into the valley. Wooden handrails with stainless steel mesh ensure visitors’ safety, in a refined, natural style.”
The landscaping includes a totem at the site entrance marking the Le Jambon viewpoint, parking spaces for cars and bicycle racks, benches and an information board. The aim is to make the most of the site’s tourism potential while respecting the natural surroundings.
“This project is an excellent reference for TMI,” concludes a proud Grégory Cimino, a few weeks before the official opening. “On the one hand, it demonstrates all our know-how, and on the other, it is an attractive tourist destination in its own right, guaranteeing maximum visibility.”

Question about this story? Ask your question
Who worked on it
Le Jambon in Vresse-sur-Semois
- steelwork contractorTMI
Keep following this
Get an email when a new story is published. No account needed.
- ProjectLe Jambon
- ThemeMaterials with a lower environmental impact
- SubjectPublic space
- CompanyTMI