Major refurbishment for bridge in Arendonk

Text Thierry PfleidererImage Renotec

Enkele jaren geleden werd Brug 5 aan de Voorheide te Arendonk door het Agentschap Wegen en Verkeer onder verscherpt toezicht geplaatst.
Enkele jaren geleden werd Brug 5 aan de Voorheide te Arendonk door het Agentschap Wegen en Verkeer onder verscherpt toezicht geplaatst.

The road bridge at Voorheide in Arendonk, over the Dessel-Turnhout-Schoten Canal, is undergoing a major refurbishment. Tim Sneyers, project manager at Renotec, and his experienced team are carrying out concrete repairs and installing a new bridge deck slab, waterproofing, bridge deck joints and road pavement. They are using the latest techniques, taking the utmost care and working to a tight schedule. The bridge bearings are also being treated again. They will be accessed by jacking the bridge up slightly. This will ensure the bridge has a service life of many more years.

Several years ago, Bridge 5 at Voorheide in Arendonk was placed under increased surveillance by the Agentschap Wegen en Verkeer. Damage had been found to the bridge deck, and the bridge’s stability was gradually being put at risk. A major renovation could no longer be postponed, and Renotec was awarded the contract. Initially, a conventional bridge renovation was chosen. The impact of repairs on both the budget and the environment is much smaller than that of building a new bridge.

The road bridge at Voorheide in Arendonk, over the Dessel-Turnhout-Schoten Canal, is undergoing a major refurbishment.

Hidden damage discovered

Although it was initially thought that extensive repairs based on local concrete repairs, applying a new waterproof membrane and laying a new asphalt surface would suffice, it soon became clear that there was more to the problem. Analysis of samples taken from the concrete bridge deck revealed that the concrete deck slab had been severely damaged by chlorides. There was no waterproof layer between the asphalt and the concrete bridge deck, allowing water, de-icing salts and oil to penetrate the concrete. To resolve the problem effectively and durably, it was decided to replace the entire deck slab, retaining only the longitudinal reinforcement in the main beams. This naturally called for a very different approach, considerably increased complexity and an even tighter schedule. 

Hydrodemolition

The bridge deck between the main beams is removed by drilling and sawing, cutting the deck into several smaller sections and taking them away. To remove the top layer of concrete, approximately 20 cm thick, over the main beams, Renotec uses hydrodemolition. This technology uses high-pressure water to remove concrete to the required depth without damaging the reinforcement. “For stability reasons, the damaged concrete is removed in a chequerboard pattern,” explains Tim Sneyers. “This means working in stages, removing only sections of concrete at a time, then installing new reinforcement and pouring new concrete in those areas. The remaining sections are tackled in the next stage. The work proceeds square metre by square metre, creating the chequerboard pattern.”

Analysis of samples taken from the concrete bridge deck revealed that the concrete deck slab had been severely damaged by chlorides.

Reinforcement must be replaced

Because chlorides are present in the concrete, the reinforcement is pitted in many places or has rusted through. New reinforcing bars and links therefore have to be installed. “It’s not an easy task,” says Tim Sneyers, “because the existing bridge plans often differ from the actual situation. So each time, we have to inspect the site to determine where and how the new reinforcement can be installed.”

Renotec is carrying out concrete repairs and installing a new bridge deck slab, waterproofing, bridge deck joints and road pavement.

Tight schedule and safe surroundings

As work progresses, Tim Sneyers and his team have quickly realised that the Voorheide bridge in Arendonk is a strategic link in the municipality. Closing the bridge to road traffic therefore has a major impact on life in the village centre. The challenge for Renotec is to complete the renovation of the road section as quickly as possible. This tight schedule means long working days, weekend work and flexibility from the motivated Renotec team. Meanwhile, the cycle bridge alongside the road bridge is seeing even heavier use. “This puts extra pressure on us to ensure safety and keep disruption, such as noise, to a minimum. Work is still in full swing. We plan to complete the sustainably refurbished bridge in September,” concludes Tim Sneyers. ■

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBrug 5 aan de Voorheide
  • ThemeExtending the life of bridges and tunnels
  • SubjectConcrete
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.