De Vlaamse Waterweg submits amendment request for Steenbruggebrug environmental permit

De Vlaamse Waterweg submits amendment request for Steenbruggebrug environmental permit

De Vlaamse Waterweg nv is submitting an amendment request for the environmental permit application to build the new Steenbruggebrug. This marks a fresh start following the earlier annulment of the permit decision. In the most favourable scenario, work could begin in early 2027. A new public inquiry will take place during January 2026.

De Vlaamse Waterweg nv wants to replace the existing Steenbruggebrug with a high-level fixed road bridge and a movable cycle bridge. This will allow road traffic to cross the Ghent-Ostend Canal smoothly at all times. Straightening the bend will remove a navigational bottleneck for inland shipping and create space for wetland habitat.

From the moment an appeal was lodged against the permit granted, discussions were held with the appellants and solutions were sought. Agreements have been reached with several stakeholders to enable the project to proceed.

De Vlaamse Waterweg nv is now submitting an amendment request as part of the current environmental permit procedure for the Steenbruggebrug project. The amendment request will be followed by a new public inquiry, which will begin during January 2026. The plans and documents can be viewed online for the duration of the public inquiry via the environmental permit portal www.omgevingsloket.be or during opening hours at OostCampus in Oostkamp or Huis van de Bruggeling in Brugge. 

Intensive work

The amendment request includes various major and minor changes arising from earlier appeals and objections, evolving insights among the partners and stakeholders involved, changes in legislation and updates to the documents. Intensive work on this has been under way since the start of the appeal procedure.

Brugge and Oostkamp are closely involved in this process and will continue to monitor the effects on local mobility and the living environment.

The changes include new access routes during and after the works, as well as improvements to accessibility in the new layout. The structural designs of the bridges and the realignment of the bend itself will remain unchanged.

The project partners hope that the solutions set out in the amendment request will help the project progress smoothly. It will have a positive impact on mobility, safety and quality of life in the southern outskirts of Brugge and in Oostkamp.

Investing in the future of inland shipping

The new bridges at Steenbrugge and the realignment of the bend in the Ghent-Ostend Canal are part of the cross-border Seine Schelde inland waterway project, which receives support from the European Union.
The entire project is co-funded by Agentschap Wegen en Verkeer, the city of Brugge, the municipality of Oostkamp, Farys and Aquafin.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectSteenbruggebrug
  • ThemeStrengthening waterways and coastlines
  • SubjectBridges & tunnels
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.