Highly precise milling work for Circuit van Spa-Francorchamps

As part of the major renovation of Circuit van Spa-Francorchamps, required ahead of 24H SPA EWC Motos, one aspect deserves particular attention: milling off the existing surface to lay new asphalt between turns T8 and T9 and along the famous Raidillon. This was just one week’s work for specialist contractor TdeuxR, which made good use of Topcon België’s innovative technology.

TdeuxR, also known as Top-Off, is the Belgian market leader in milling off surface layers, whether on roads, airport runways, concrete slabs or other surfaces. The company works on projects of all sizes, each requiring a high degree of precision. Ivan Meuwis has headed TdeuxR for 22 years, so he knows what he is talking about: “Our strong market position means that we carry out millimetre-accurate 3D milling work every week, giving us a wealth of experience that other companies cannot match. Our client on this project was Bodarwé, which regularly calls on us for work at Circuit van Spa-Francorchamps. I think we have milled off the entire circuit twice over the years!”
Although TdeuxR did not lay the new surface course itself, it did supply the feeders, the crucial link between the asphalt paver and the finishing machine, as the required model was not available in Belgium. Thanks to its extensive network, TdeuxR was able to bring three over from the Netherlands.

Uncompromising quality
The client engaged Dromo Circuit Design, an Italian company specialising in motor racing circuits, which provided detailed specifications on the quality standards required to obtain dual FIM/FIA certification. A new section exclusively for motorcycles was built on the inside of turn T9, at Speaker’s Corner. “Dromo asked us to mill the base course in 3D before the new surface course was laid, to ensure a consistent thickness.” Turn 9 and part of the Raidillon were also milled, using a Wirgen W220 with a fine milling drum, to remove the existing surface without changing the circuit layout or gradient. This was done using models based on scans of the existing surface, to enable GPS guidance of the machine. “Even Dromo, which is used to working this way, was pleasantly surprised by how smoothly the process went and by the end result.” The quality of the work, carried out in three areas, is therefore very high.
Ivan Meuwis: “We cleaned the milled surface with a high-pressure washer before Bodarwé laid the new asphalt using its finishing machines. The deadline was very tight, but we were lucky with the weather. Early March can still bring severe winter conditions in Francorchamps, but we did not encounter any this time!”

A double first
Based on Dromo’s static scans, Topcon implemented the machine control component, RDMC (Relative Design Machine Control), of its Smoothride solution. Two GPS antennas mounted on top of the Wirgen’s cab enabled the system to continuously detect the drum’s position and compare it with the required milling depth, based on two digital terrain models (DTMs). The machine followed the relative thickness between these two levels with the help of skis on either side of the drum, which remained in contact with the existing road surface. The aim was to mill as evenly as possible, so the asphalt could be laid to a uniform thickness throughout. GPS accuracy was corrected using a total station installed in the centre of the work area and communicating via radio frequency.
This approach is distinguished from traditional practice by its high efficiency. All the preparatory work is done in advance, on a computer, resulting in a significant saving in labour during construction. Arnaud De Cnijf,
Account Manager Positioning Solutions at Topcon België: “Our customers see that investing in machine control improves their productivity and gives them a competitive advantage. This was the first time we had used RDMC on a Belgian circuit, and also the first time Topcon België had worked with Dromo. However, my colleagues at Topcon Positioning Systems had already had good experiences with them, including on similar projects at the Silverstone and Abu Dhabi circuits. We are very proud to be involved in such prestigious projects.”
Een zakelijke vraag aan Top-Off NV? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFuture-proofing roads and railways
- SubjectRoad construction
- CompanyTopcon
- CompanyTop-Off NV