42 major motorway projects in 2022

In the coming months, the Agentschap Wegen en Verkeer (AWV), together with Lantis and De Werkvennootschap, will carry out 42 motorway projects, including a series of major works on bridges and tunnels.

This year, too, major works are being carried out on motorways, tunnels and bridges. Today, Flemish Minister for Mobility and Public Works Lydia Peeters announced these 42 major projects, which will provide a total of 81 km of new or resurfaced road. The investment amounts to 476 million euros, excluding the Oosterweel works. “My policy area is one that involves substantial investment, which is a key driver of the Flemish economy. Investing in mobility means investing in prosperity. Many of our motorways need improvements in road safety, traffic flow and capacity. That is why AWV, Lantis and De Werkvennootschap are tackling no fewer than 42 motorway projects together this year,” the minister said.

A vital part of the economy
On average, 66 million* vehicle-kilometres are travelled on our main road network every day, an enormous figure for a relatively small region. Our motorways are also of great importance to European transport.
Minister Peeters is aiming for a high level of investment in our infrastructure. “Our motorways have improved in recent years, and these works will take us a step further. Nevertheless, Flanders still faces a maintenance backlog. By investing in the renovation, renewal and maintenance of our infrastructure, we are making the necessary change. This is how we build a safer, smoother-flowing and future-proof road network for the long term,” the minister said.
Tunnel and bridge works are also noteworthy, including the renewal of the lighting and wall panels in the Kennedytunnel, the construction of an emergency crossing in the Vierarmentunnel, the extensive renovation of the Leonardtunnel and the renovation of the viaduct in Vilvoorde.

Minimising disruption
Roadworks inevitably cause disruption. “So check wegenenverkeer.be before you set off,” AWV advises. “You can see exactly which works are planned on which motorways, and what disruption to expect.”
The greatest disruption in 2022 is expected on
- the E313, where the bridge at Wommelgem is being rebuilt
- the E40, where the gantries are being replaced and emergency stopping areas are being constructed at Sterrebeek
- the renewal of the Trompetaansluiting R8/A19 at Wevelgem
- the Brussels inner and outer ring road (R0), where renovation of the viaduct at Vilvoorde is starting (De Werkvennootschap)
- the E40, where two bridges at Erpe-Mere are being renewed, and
- the Antwerp Kennedytunnel, where the lighting and wall panels are being renewed.
To minimise disruption, AWV coordinates the timing of the works with partners such as Touring, VAB, Febetra, VOKA and Logistiek Vlaanderen. Major roadworks in the same area are also scheduled to avoid overlapping, and diversion routes are assessed in advance to ensure they remain free of disruption.

Safety comes first
Workers are on site around the clock. “We are taking measures to improve safety in work zones. Accidents happen every year. Stick to the speed limit, obey the signs and take extra care as you approach a work zone,” Minister Peeters urges.
Speeds at roadworks are monitored not only through manned checks, but also using semi-fixed speed cameras and mobile average-speed checks.
*Figure for the last year unaffected by coronavirus (2019).
2020 figure: 54 million. 2021 figure: 58 million.