Ryco Clubhouse, Ostend | Refurbished revetment for Ryco Ostend

Ryco, the Royal Yacht Club Oostende, is Belgium’s oldest yacht club. The clubhouse dates from 1906 and was a royal gift from Leopold II. The building stands on a peninsula protected by a natural stone slope. During the Second World War, dredging was carried out to excessive depths to accommodate the Allied landing forces, causing the building to gradually subside over the past few decades. A major renovation was needed. The Coastal Division put the works out to tender, and Herbosch-Kiere is now well underway with their execution. Work began in May 2018 and is scheduled for completion after the summer of 2019

Drilling the ground anchors on the northern side.
The first step was to stabilise the building. Around 70 micropiles (25T and 40T) were installed beneath it. These grout-injected steel piles were drilled beneath both the internal and external walls and anchored into them to prevent further subsidence. Once the grout had cured, the renovation work could continue. “A row of sheet piles was driven all around the peninsula, totalling 3,100 m² of AZ42-700,” explains Geert Stellamans, project engineer at Herbosch-Kiere. “A reinforced concrete toe beam will be built on top, with recesses for installing the ground anchors. In total, there is a 160 m wall with 85 recesses for the ground anchors, each with a service load of 60-65 tonnes.”
A monitoring programme was in place during the pile-driving works to track vibrations. Geert Stellamans: “Two vibration meters were installed in the listed building, one on the ground floor inside the workshop and one at the highest point, in the tower. The use of a high-frequency vibratory hammer with variable moment meant that no unacceptable vibrations were recorded. Once the ground anchors have been drilled and have cured sufficiently, work can begin on removing the old revetment on the water side of the sheet pile wall. This old slope consists of a top layer of natural stone and underlying layers of masonry. In total, around 6,000 m³ will be dredged from in front of the sheet pile wall using a pontoon equipped with a heavy-duty hydraulic excavator. This also includes removing 4,000 m³ of contaminated silt, which will be dredged separately and taken to a treatment centre.”

Grinding off the excess length of the ground anchor tendons and fitting protective grease caps to the anchor heads.
New slope
A new slope is planned on the landward side of the sheet pile wall. A doubly reinforced concrete slab will protect the spit and provide a foundation for the new natural stone facing. “Around 1,100 m² of BHS is planned for this facing,” says Geert Stellamans. “To prevent excess water pressure building up behind the slope slab, which is in a tidal zone, a full drainage system will be installed beneath it in a crushed concrete fill, amounting to around 3,000 m³. A specific geotextile, covering 4,000 m², will be laid on the ground slope during installation of the drainage to prevent soil loss through the drain. The work at the western tip of the peninsula is unusual. Because the tip is curved, it is not possible simply to use ground anchors perpendicular to the toe beam. In that arrangement, they would all point towards one another and meet at the same point. The final solution combines ground anchors drilled parallel to the angle bisector of the curve with tie rods connecting the southern and northern toe beams to prevent the curve from opening up. Micropiles were also installed, with several yokes distributing all the forces.”

Western side: anchor recesses for the ground anchors, dowel connection to the sheet pile wall and tie rod connectors.
New slipway
A walkway is being built to provide access to the floating pontoons. An aluminium bridge will then be installed on it to provide access to the floating pontoons. As the total length of floating pontoons will increase in the final configuration, around four new tubular piles will also be installed as anchor points. Geert Stellamans: “A new slipway is planned on the southern side of the island for launching and retrieving yachts. This concrete ramp will be partly integrated into the refurbished slope. The lower section of the slipway, from +3 m TAW to +1 m TAW, consists of a number of tubular piles with a precast concrete superstructure. The design provides for this option because the working window at this sea level is too short to complete everything in situ. A working platform is also planned at the top of the slipway. It too consists of a few tubular piles with a steel superstructure. Azobé fendering will be fitted to the waterside of the slipway and working platform piles to protect the yachts when they come alongside.”

Pile driving for the tubular piles that will anchor the floating pontoons.
Alongside the work on the water, work is also under way on land. The entire sewer system will be renewed, with rainwater recovery, installation of a micro-treatment plant, grease separator, inspection chambers, siphon chambers and new electricity conduits. “The finishing works for the superstructure include 1,050 m² of Kandla sett paving. A number of benches, grass strips and a refurbished cast-iron railing, mounted on a natural stone kerb, will provide the finishing touch. This will leave the Ryco clubhouse and peninsula ready to withstand the sea for decades to come. From a scheduling point of view, coordinating all these activities smoothly was no easy task, especially given that the work area is tiny and the yacht club has remained operational, with its restaurant open. We would like to thank the Ryco team and the operator for their unfailing commitment and patience,” concludes Geert Stellamans.
Een zakelijke vraag aan Herbosch-Kiere? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectClubgebouw Ryco
- SubjectPublic space
- CompanyHerbosch-Kiere