BESIX showcases its strengths as a one-stop shop on rail project

BESIX Vlaanderen, BESIX Infra en Van den Berg sloegen de handen in elkaar voor de verbreding van de spoorlijn Aalter-Beernem van twee naar vier sporen, in opdracht van TUC RAIL.
BESIX Vlaanderen, BESIX Infra en Van den Berg sloegen de handen in elkaar voor de verbreding van de spoorlijn Aalter-Beernem van twee naar vier sporen, in opdracht van TUC RAIL.

BESIX Group is involved in every phase of the project in Aalter-Beernem: BESIX Vlaanderen, BESIX Infra and Van den Berg, another BESIX subsidiary, joined forces to widen the Aalter-Beernem railway line from two tracks to four, on behalf of TUC RAIL. The project covers a total route of around 8 km and has a budget of 37 million euros. From design through to handover, BESIX Group showcased its strengths as a one-stop shop. “By keeping everything in-house and acting as a single point of contact, we were able to complete this project on time and within budget,” says Dieter Van Parys, project manager at BESIX.

With the expansion to four tracks, freight traffic between Aalter and Beernem is now separated from passenger services, and train frequency has increased. The existing ditches and roads along the route were relocated and renewed. The Aalter and Maria-Aalter stops were also completely redeveloped. The design was a joint undertaking by BESIX, BESIX Infra and TUC RAIL. BESIX was also responsible for all earthworks, preparing the track formation, overhead line foundations and renewing the two stations, Galgenveldbrug and the retaining walls … Van den Berg, in turn, took care of the cable ducts and utility lines. “Finally, BESIX Infra handled the roadworks, hydraulic engineering, fencing and platform equipment,” says Thierry Fonteyne, roadworks and drainage site manager at BESIX Infra.

From design through to handover, BESIX Group showcased its strengths as a one-stop shop.

Involved from A to Z

The project was developed in 3D to the greatest extent possible. Advanced drone surveys were among the techniques used to map the existing conditions. This helped produce a more accurate construction design that took account of all the constraints set by the various departments at TUC RAIL, Infrabel and NMBS. The design work was carried out in close collaboration with the BESIX Engineering Department. 

Thierry Fonteyne: “We see it as a major benefit that BESIX and BESIX Infra were involved in the project from the study and design phases onwards. This enabled us to work with the client to find the right solutions and working methods. For example, when Van den Berg excavated the cable trenches, the trench support had to be installed using a sliding formwork machine. BESIX Infra’s expertise proved invaluable. This meant that for every task on the project, we could draw on the know-how and expertise of a company within BESIX Group.”

“Thanks to the one-stop-shop approach, combined with our experience and know-how, we were able to deliver this project on schedule and within budget.”

Collaboration

This was the first project for which a temporary joint venture with BESIX Group was set up. Collaboration was therefore the common thread throughout the project. This was a major asset, as bringing in the earth, along with all the other materials, presented a logistical challenge. The route was difficult to access and there were many sections without access roads, meaning all transport had to travel along the track formation. 

Dieter Van Parys: “The major advantage is that we can operate as a one-stop shop. There are no hidden agendas among those involved, which greatly facilitates collaboration. Of course, we also faced the typical challenges of railway work: tight timings, safety, working at night, keeping employees motivated … It was certainly no easy task, but thanks to the one-stop-shop approach, combined with our experience and know-how, we were able to deliver this project on schedule and within budget.” 

With the expansion to four tracks, freight traffic between Aalter and Beernem is now separated from passenger services, and train frequency has increased.

One-stop-shop app

Clients see BESIX’s ability to design and deliver projects from A to Z as a one-stop shop as a major benefit. Dieter Van Parys: “This gives us a significant competitive advantage and leaves the client satisfied with a complete solution for the entire project. We have all the expertise within the group to see projects like this through from start to finish. BESIX Engineering, BESIX Vlaanderen for civil engineering, BESIX Infra for roads and hydraulic engineering, Van den Berg for cables and utilities, Franki Foundations for foundation engineering, BE-Inject for ballast bonding … The successful project between Aalter and Beernem has certainly paid off for us, as we are now carrying out a similar project on the same railway line between Erpe-Mere and Aalst.” 

Internally, too, employees are increasingly looking within their own group for specific expertise. “We even developed a one-stop-shop app for this purpose. It enables employees to easily find the right expert for a particular task within BESIX Group,” concludes Dieter Van Parys.     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFuture-proofing roads and railways
  • SubjectYearbook
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.