Albertkanaal bridge raising, Cluster 2 perfectly on schedule

Following the successful completion of the first cluster of 7 bridges, De Vlaamse Waterweg appointed nv Via T Albert, comprising Franki Construct, Willemen Infra, HYE and Aelterman, to tackle the second cluster of 8 bridges over the Albertkanaal. In this article, Franki Construct and Willemen Infra, both part of Willemen Groep, share their insights into this major, complex PPP project. It forms part of the overall upgrade of the Albertkanaal, which will see the navigable clearance beneath a total of 62 bridges increased to 9.10 m. “For now, we are perfectly on schedule. Six of the 8 bridges are back in operation, and we expect to complete the cluster as planned by summer 2022,” says Bert Muys (Franki Construct), who is coordinating the project as a whole.

With almost 40 million tonnes of goods transported each year, the Albertkanaal is the most important waterway in Flanders. Container traffic in particular has risen sharply over the past decade. As part of efforts to increase the capacity of the Albertkanaal, De Vlaamse Waterweg nv is investing in its further development. The current limits on navigable height and width beneath the bridges are a bottleneck for inland shipping on the Albertkanaal. Raising the bridges over the canal to provide a navigable clearance of 9.10 m will allow inland vessels carrying four layers of containers to navigate safely and smoothly. It will also create better opportunities for Short Sea Shipping on the Albertkanaal.
PPP project under a DBFM contract
At the end of April 2019, De Vlaamse Waterweg and Via T Albert signed the contract for the second cluster of the ‘Verhoging bruggen Albertkanaal’ PPP project. The two parties entered into a public-private partnership (PPP) covering the design, construction and financing (EPC), as well as 30 years of maintenance (MTC), for eight bridges: Beringen, Paal-Tervant, Meerhout-Vorst, Lummen, Oelegem, Herentals, Kuringen and Schoten. Bert Muys: “Cluster 2 is a PPP project under a DBFM contract, in which the client, De Vlaamse Waterweg, has partnered with nv Via T Albert. This temporary joint venture brings together four specialists: Franki Construct is responsible for the civil engineering works, Willemen Infra handles the road and drainage works, Aelterman contributes its steel construction expertise, and HYE brings its water engineering expertise to the project. I am project director for the EPC phase. The maintenance phase begins once the EPC phase is complete. During that phase, we must meet all the specified and promised requirements in order to receive a completion certificate.”

Experience from Cluster 1
The fact that nv Via T Albert had already delivered a first cluster of 7 bridges is now proving to be a major advantage. “With Cluster 1, the client still had a lot of questions about the design, but we were able to start Cluster 2 on a strong foundation of trust,” says Bert Muys. “From the outset, they trusted us to take care of things in the right way. This meant a shorter study period at the outset, with the same engineering consultancies as for Cluster 1. After financial close in April 2019, the study period lasted around 6 months, and the first works began in January 2020. A carefully devised schedule was absolutely crucial to delivery, for ourselves, the client and the stakeholders alike. In this respect too, the experience gained on Cluster 1 was invaluable. We are proud to say that we are currently right on schedule. Six of the eight bridges have already been completed. Work is still continuing on the quay walls, towpaths and adjacent road network, with a strong focus on minimising disruption. We aim to complete the entire cluster by summer 2022.”
Civil engineering works
As with Cluster 1, Franki Construct played a leading role in the civil engineering works for the PPP project. “Our work includes bridge construction, concrete, reinforcement and foundation works for the bridges, and the construction or reinforcement of retaining walls and quay walls,” explains Davy Vrijsen, site manager at Franki Construct. “We also provide the assembly area and temporary facilities needed to get the bridge to and from the water. The bridges are not simply being raised, the canal is also being widened on site from 50 to 80 metres. In broad terms, those are the works carried out by Franki Construct.”
Franki Construct is also drawing on its experience from Cluster 1 to optimise the works on Cluster 2. Davy Vrijsen: “For example, we have taken a different approach to site management. On Cluster 1, a site manager was assigned a specific task, such as bridge construction or quay walls, across all eight sub-projects. Logistically, however, this was not ideal, as the person in charge regularly had to rush from one site to another. For Cluster 2, we chose to appoint one site manager per sub-project, responsible for overseeing it from start to finish. As site manager, I drew up a clear schedule for each sub-project, so that the people on site only see the plans for their specific bridge.”

17 canal-closure weekends
Scheduling is crucial not only for the PPP project as a whole, but especially for the civil engineering works. Davy Vrijsen: “We have 17 canal-closure weekends available for the entire cluster. That is a particular challenge when you consider that one bridge would normally require 4 closure weekends. This means that during a closure weekend we combine work on several sub-projects, carrying out critical tasks such as striking formwork, floating in bridges and demolition at three different sites. You can imagine how important the overall schedule is. Franki Construct’s strength in this area, and that of the wider Willemen Groep, is undoubtedly the expertise we have in solving complex logistical puzzles. It is in our DNA.”
Road and drainage works
While Franki Construct is responsible for the civil engineering works, Willemen Infra brings added value to the project through its road and drainage works. “On the one hand, we are surfacing the approach ramps and bridge deck to complete the main route across the canal, and on the other, we are building the cycle paths and towpaths. We are doing this for all the sub-projects,” says Moric De Koninck, project director at Willemen Infra. “As this is a PPP project, our role is not limited to construction. A great deal of design work was also involved, which makes it particularly interesting. Numerous conditions and requirements were set, and we had to take these into account during construction. We then looked for the most economical and feasible solutions.”
Willemen Infra’s operations across Flanders are a major asset, and particularly so on a project of this scale. Moric De Koninck: “We were able to carry out the works between Schoten and Kuringen, where the 8 bridges are located, using our own staff from the northern and eastern regions. This naturally requires a great deal of coordination, and it is crucial to deploy our people in the right places. Our regional spread also means we can have our teams led by site managers from the same region, allowing us to draw on our locally rooted strengths. There was also excellent coordination across the wider organisation. The sub-project in Beringen is a good example. Willemen Infra’s northern, eastern and western regions worked together there on the asphalt, concrete, drainage and foundation works.
Transporting materials by water
For Willemen Infra too, clear communication, good coordination and the necessary flexibility are essential to achieving a successful outcome on this project. Moric De Koninck: “That applies not only between Willemen Infra’s different regions, but also between Willemen Infra and all the other parties. We can certainly say that the collaboration has been good, allowing the works to get under way quickly. Willemen Infra also appointed one site manager per sub-project. That works very well, and we managed to complete all our road, foundation and drainage works entirely to schedule and within the deadlines. It is great to see how Willemen Infra’s different regions worked together and supported one another. That was the only way we could deliver high-quality bridges in a short time.”
Minimising disruption
Minimising disruption was a priority and a guiding principle throughout the entire cluster. For example, most materials were transported to and from the sites by water, temporary bridges were installed at the various sites to limit disruption to the surrounding area, and the canal-closure weekends were grouped together as efficiently as possible. The strong commitment to carrying out the works with minimal disruption for all stakeholders, combined with a creative approach to delivery, was nv Via T Albert’s greatest asset in winning the contract for the second cluster too.
“Willemen Groep has traditionally placed a strong focus on minimising disruption, and it was certainly a decisive factor on this project. We deliberately looked for a highly practical yet ingenious way to add value. The geographical spread of the project was a challenge, but we addressed it by grouping canal-closure weekends across different sub-projects. Each sub-project had its own milestones, which meant that a closure was unavoidable. By grouping the work, we were able to limit the number of canal-closure weekends to 17. When we embark on one of these weekends, we are therefore working on several fronts at once. On 15 November, for example, the new bridge at Kuringen was floated into place while the old bridge at Oelegem was being demolished. In a single weekend, we make enormous progress. This perfectly illustrates the significant added value Willemen Groep brings to this PPP project. Together with all our subcontractors, we make sure everyone is working towards the same goal. And that is the key to success,” concludes Bert Muys.
Question about this story? Ask your question
Who worked on it
Verhoging bruggen Albertkanaal – cluster 2
- clientDe Vlaamse Waterweg
- tijdelijke maatschapnv Via T Albert
- civil engineering worksFranki Construct
- wegenis- en rioleringswerkenWillemen Infra
- staalbouwexpertiseAelterman
- kennis in de waterbouwsectorHYE
Keep following this
Get an email when a new story is published. No account needed.
- ProjectVerhoging bruggen Albertkanaal – cluster 2
- ThemeExtending the life of bridges and tunnels
- SubjectYearbook
- CompanyDe Vlaamse Waterweg
- Companynv Via T Albert
- CompanyFranki Construct
- CompanyWillemen Infra
- CompanyAelterman